BLD00-02899
| FIRE-Final Inspection | 3/14/2001 | 3/15/2001 | 3/15/2001 12:00:00 AM | A | PASS |
|
|
###-#### fire fn--allan
|
BLD00-00746
| FIRE-Final Inspection | 3/14/2001 | 3/15/2001 | 3/15/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/14/2001 at 13:22:40. Contact: ###-####. plans on the outside at south end of the building 3/15/2001 9:32:39 AM
|
FIR00-00627
| INSP-Sprinkler Rough-in/Hydro | 3/14/2001 | 3/15/2001 | 3/15/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 03/14/2001 at 15:22:22. Contact: ###-####. hydro on all wet systems okay 3/15/2001 1:16:21 PM
|
BLD00-03531
| FIRE-Final Inspection | 3/14/2001 | 3/15/2001 | 3/15/2001 12:00:00 AM | A | FAIL |
|
|
matt-- ###-#### fire fn occupant load sign; detectors for AHU shutdown; air balance report for hood system; tested suppression system - okay 3/15/2001 2:08:49 PM
|
BLD01-00189
| FIRE-Final Inspection | 3/15/2001 | 3/15/2001 | 3/15/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
BLD00-02964
| FIRE-Final Inspection | 3/14/2001 | 3/15/2001 | 3/15/2001 12:00:00 AM | P | PASS |
|
|
###-#### early pm call first to meet there
|