Inspections for the day of: Thursday, March 15, 2012.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR12-00054 INSP-Sprinkler Rough-in3/15/20123/15/20123/15/2012 3:53:59 PMPFAIL
Sprinkler heads are blocked by hvac roof penatrations/duct work in three locations. The head spacing shall meet NFPA 13 8.6.5.2.1.2 and 8.6.5.1.2. Unfortunatly some of this work is located in a remote hydraulic area. Also a soffit has been added at the main entry that was not shown on the plans. At this soffit the fitter added two additional heads. This now puts five heads on an 1 1/4" line where the remote area is flowing four heads off of 1 1/2" (1 1/4" branchline with 1 1/2" riser nipples). After speaking with Tim Frost it was determined that plan modifications will be needed prior to a final sign off showing all changes.
FIR10-00033 INSP-Final Inspection3/15/20123/15/20123/15/2012 2:27:46 PMPPASS
Permit finaled
FIR11-00607 INSP-Conference3/15/20123/15/20123/15/2012 2:12:34 PMPDONE
I spoke to jeff about an additional fitting and elevation change in the piping out on the dock. He was going to get with his designer and then with Tim Frost to verify that the hydraulic calculations were still acceptable.
BLD10-01738 FIRE-Conference3/14/20123/15/20123/15/2012 2:11:09 PMADONE
I stopped at job site and the receptionist contacted Jesse and we spoke over the phone about getting the life safety inspection performed. He stated that the new fire hydrant would not be installed for another 3 weeks. I set up a re-inspection conference for three weeks from now for a follow up.
BLD12-00196 FIRE-Final Inspection3/14/20123/15/20123/15/2012 9:33:25 AMAPASS
life safety passed