ESC11-00732
| Conference | 3/15/2012 | 3/15/2012 | 3/15/2012 3:21:57 PM | P | FAIL |
|
|
Verbal to RP: Replace all top soil that eroded from the sheeting across the green belt into the Wise way corridor and remove all sediment deposits form the event that discharged into the wetland area. Also gave thee option to the RP to plug off the three outlets from the pond that outfall into the Wallings corridor to eliminate a turbid discharge. Will follow up on
|
ESC11-00879
| BMP Violation | 3/15/2012 | 3/15/2012 | 3/15/2012 3:07:55 PM | P | PART |
|
|
Activily cleaning up the street. Also have deverted all storm water run off through the project area on the street back into the project. All storm water runoff from the water shed area above the project is deverted into the storm water pond above the project area.
|
ESC12-00036
| General Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 3:00:29 PM | | PASS |
|
|
No activity on this portion of the project due weather and site conditions.
|
ESC11-00762
| General Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 2:59:31 PM | | PASS |
|
|
|
ESC12-00024
| General Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 2:59:15 PM | | PASS |
|
|
|
ESC11-00525
| General Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 2:58:05 PM | P | CANC |
|
|
wrong date.
|
ESC11-00525
| Site Preparation | 10/7/2011 | 3/15/2012 | 3/15/2012 2:57:16 PM | A | PART |
|
|
Waiting on a letter of extention of the permit from Brighton Development. Will follow up in one week.
|
ESC11-00609
| General Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 8:02:13 AM | | FAIL |
|
|
Message to RP: Cleanup the sediment discharge offo f the hardsurfaces where a concerated flow was generated at the driveway and wattle meet. Install an additional sediment barrier to minumize any additional turbid discharges off of the disturbed soil onto the sidewalk to the gutterpan. Will follow up on 3/16/2012.
|
ESC11-00590
| General Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 7:55:54 AM | | PASS |
|
|
No actvity due to weather conditions.
|