FIR13-00011
| INSP-Sprinkler Rough-in | 3/11/2013 | 3/12/2013 | | P | |
|
|
This is for the 3rd, 4th & 5th Fl. Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
FIR11-00228
| FIR-Aging Inspection | 3/15/2013 | 3/15/2013 | 3/21/2013 7:52:23 AM | | DONE |
|
|
|
BLD13-00055
| FIRE-Conference | 3/15/2013 | 3/15/2013 | 3/15/2013 5:10:30 PM | A | DONE |
|
|
On site meeting with Rich from Govt. buildings, T. Gainor and J. Blais regarding conditions per IFC for delayed egress. Verified new exit signs and EM lighting have been installed per previous inspection. Determined tie in to the FA system is also required unless verification of an alternate approval is provided.
|
BLD12-02191
| FIRE-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 4:56:51 PM | P | PASS |
|
|
Fire life safety okayed pending max. occupant signage is posted per plan review and red-line annotations, night latch at the south exit door removed while on site.
|
FIR13-00008
| INSP-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 4:52:44 PM | P | PASS |
|
|
Fire alarm testing completed and passed after adjustments made while on site. Permit finaled.
|
BLD13-00175
| FIRE-Final Inspection | 3/15/2013 | 3/15/2013 | 3/15/2013 4:47:07 PM | P | PASS |
|
|
Noted correction items completed. Fire life safety passed.
|
BLD13-00218
| FIRE-Final Inspection | 3/15/2013 | 3/15/2013 | 3/15/2013 4:45:35 PM | P | PASS |
|
|
Verified noted correction items are finished. Life safety finaled.
|
BLD13-00489
| FIRE-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 4:43:25 PM | P | PASS |
|
|
Fire life safety inspection passed provided the fire extinguisher is relocated adjacent to the main exit as discussed.
|
FIR13-00011
| INSP-Sprinkler Rough-in | 3/14/2013 | 3/15/2013 | 3/15/2013 4:40:26 PM | A | PART |
|
|
Completed shell fire protection rough-in at floors 7 and 8. Noted missing hangers at floor 8, beam obstruction at the fire service elevator lobby typical per floor.
|
FIR13-00059
| INSP-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 4:35:29 PM | A | PART |
|
|
Scope of work complete, functional testing passed. Final pending as-builts per red line plan review note comments.
|
FIR12-00038
| INSP-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 4:30:38 PM | A | PASS |
|
|
Functional testing passed 3/14. Fire alarm permit finaled.
|