Inspections for the day of: Tuesday, March 15, 2016.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00356 General Inspection3/15/20163/15/20163/17/2016 12:50:04 PM PASS
Yard landscaped, building materials removed as requested and DI bag on Ashtree was taken out. ESC permit conditions satisfied.

Approved.
ESC15-00360 General Inspection3/15/20163/15/20163/16/2016 3:56:41 PM CANC
ESC16-00156 BMP Violation3/8/20163/15/20163/16/2016 3:37:48 PMAPASS
Check for construction entrance installation

Construction entrance installed with 2-3 inch rock. Sweeper unit now kept on site. No trackout observed and conditions are wet/muddy within site. DI bags installed. Silt fence and vegetative buffer along creek are undisturbed.
ESC15-00354 Aging Inspection3/15/20163/15/20163/16/2016 3:29:24 PM PASS
Home near completion. Driveways are installed, trash and materials are contained, no wind blown debris. Site will soon be landscaped. No corrections.
ESC15-00353 Aging Inspection3/15/20163/15/20163/16/2016 3:27:19 PM PASS
Home near completion. Driveways are installed, trash and materials are contained, no wind blown debris. Site will soon be landscaped. No corrections.
ESC14-00338 General Inspection3/15/20163/15/20163/16/2016 3:12:57 PM PEND
No activity. Parcel now has for sale sign on it. No ESC issues, will be expired next general inspection.
ESC15-00378 General Inspection3/15/20163/15/20163/16/2016 12:59:22 PM PASS
WIP. Will need to stabilize disturbed road shoulder downhill from driveway. No trackout. Hillside BMPs installed. Runoff down to Hill Road is clear.

Note: Pre-existing DI bag is full of dirt and leaves Will make note to ACHD maintenance crew
ESC15-00453 General Inspection3/9/20163/15/20163/16/2016 12:13:55 PMPPASS
No trackout. No discharges offsite to street. Runoff to vegetated area through wattle is not visibly carrying stucco waste, which still needs cleaning.

No corrections issued, home near completion so will be cleaned soon.
ESC15-00019 General Inspection3/15/20163/15/20163/16/2016 8:37:15 AM PASS
Canal intake structure is complete. Disturbed areas around intake have been hydroseeded. No corrections associated with this phase. See also ESC15-00306
ESC15-00221 General Inspection3/15/20163/15/20163/15/2016 9:23:17 AM PASS
ESC13-00755 General Inspection3/15/20163/15/20163/15/2016 7:56:28 AM CANC