Inspections for the day of: Monday, March 16, 1998.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD96-02800 INSP - Framing/Rough-in3/13/19983/16/19983/16/1998 12:00:00 AMANR
YOU TALKED TO JOE ABOUT THIS ON FRIDAY ###-####...need firestop penetrations at 1hr lid mens, women's shower rms. ok to begin concrete board placement, will reinsp pm
BLD97-03298 INSP - Concrete3/16/19983/16/19983/16/1998 12:00:00 AMAPART
met w/ owner,discussed eng'g
BLD98-00003 INSP - Concrete3/16/19983/16/19983/16/1998 12:00:00 AMANR
chk'd job, swo placed 3-13
BLD98-00263 INSP - Framing/Rough-in3/16/19983/16/19983/16/1998 12:00:00 AMAPART
333 area, demising walls ok, if elec ok
BLD97-03341 INSP - Framing/Rough-in3/17/19983/16/19983/16/1998 12:00:00 AMPPASS
CN OK...REC'D ENG'S LETTER
BLD97-03341 INSP - Energy code compliance3/13/19983/16/19983/16/1998 12:00:00 AMPPASS
reinspection tim ###-####-pager
BLD97-01942 INSP - Foundation3/16/19983/16/19983/16/1998 12:00:00 AMPNR
mark ###-####...NR, NEED GAS CO OK OR MOVE LINE AND OK FOR LARGE CONCRETE PIPE AT FTG, CANNOT POUR FTGS ON PIPE.
MEC98-00827 INSP - Framing/ Rough-in3/16/19983/16/19983/16/1998 12:00:00 AMPNR
REMODEL--R/I AND PRESS ###-####...COULDN'T FIND, WILL RECHECK 3-17
BLD96-02800 INSP - Framing/Rough-in3/16/19983/16/19983/16/1997 12:00:00 AMPPART
4:00 w/ ormond & comm'l const re shafts, reinsp shower area lid SHAFTS OK IF ORIGINAL DETAIL FOLLOWED TO "REMOVE" (COVER) ALL MAJOR STRUCT. ELEMENTS...JOISTS, BEAMS, ETC. OK TO FIRE CAULK NON-CRITICAL ELEMENTS...ALL-THREAD, BRACES, ETC. OK TO COVER SHOWER COMPARTMENT AT MENS LOCKER ROOM