ELE01-00412
| Electrical Rough-In | 3/15/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | A | PASS |
|
|
###-####. underfloor raceway; ceiling ele r/i. ok. 3/16/2001 9:36:16 AM
|
ELE00-01032
| Final | 3/15/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | A | PASS |
|
|
###-#### jerry. generator field-evaluation test performed, certificate/results faxed to building department. verification of tag on equiptment was performed. ok. 3/16/2001 10:33:22 AM
|
ELE01-00445
| Permanent Service | 3/15/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | A | PART |
|
|
###-####. 3/15/2001 4:12:45 PM. grounding ufer conductor ok. 3/16/2001 8:49:16 AM
|
ELE01-00824
| Electrical Rough-In | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PART |
|
|
###-####. concession stand recepticle outlets/lighing ele r/i, ok. 3/16/2001 10:54:07 AM
|
ELE01-00833
| Electrical Rough-In | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PART |
|
|
CONFERENCE ###-#### Jim. discussed grounding/bonding for main service switch gear. 3/16/2001 3:23:28 PM
|
ELE01-00086
| Final | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PASS |
|
|
###-#### LOCK IT UP WHEN DONE. completed. ok 3/16/2001 3:24:22 PM
|
ELE01-00093
| Final | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PASS |
|
|
###-####. completed. ok 3/16/2001 3:25:00 PM
|
ELE01-00185
| Final | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PASS |
|
|
completed. ok. 3/16/2001 3:25:39 PM
|
ELE01-00312
| Final | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PASS |
|
|
completed. ok. 3/16/2001 3:26:25 PM
|
ELE01-00313
| Final | 3/16/2001 | 3/16/2001 | 3/16/2001 12:00:00 AM | P | PASS |
|
|
lock door on the way out. completed. 3/16/2001 3:27:18 PM
|