Inspections for the day of: Friday, March 16, 2001.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00268 BLD-Foundation3/14/20013/16/20013/16/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/14/2001 at 11:41:31. Contact: ###-####.wip-appears ok-hd not installed at time of inspection. 3/16/2001 12:19:13 PM
MEC00-03448 Final3/15/20013/16/20013/16/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 03/15/2001 at 13:10:54. Contact: ###-####.
MEC00-03873 Final3/15/20013/16/20013/16/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 03/15/2001 at 14:42:35. Contact: ###-####.
BLD00-03620 BLD-Energy code compliance3/15/20013/16/20013/16/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 03/15/2001 at 14:58:26. Contact: ###-####.
BLD01-00136 BLD-Framing/Rough-in3/15/20013/16/20013/16/2001 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 03/15/2001 at 15:54:17. Contact: ###-####.C. N posted 3/16/2001 11:24:21 AM
BLD00-03705 BLD-Framing/Rough-in3/15/20013/16/20013/16/2001 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 03/15/2001 at 17:04:25. Contact: ###-####. C/N issued-Do not insulate 3/16/2001 12:08:06 PM
BLD00-03704 BLD-Conference3/15/20013/16/20013/16/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 03/15/2001 at 17:05:35. Contact: ###-####. SHEAR-PARTIAL-C/N ISSUED AT FRONT, RE-INSPECTION OF REAR REQUIRED--OK TO SIDE EXCEPT REAR. 3/16/2001 11:37:03 AM
BLD01-00519 BLD-Foundation3/16/20013/16/20013/16/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 03/16/2001 at 07:45:41. Contact: ###-####.wip--appears ok-no hd installed at time of inspection. 3/16/2001 2:31:47 PM
BLD01-00248 BLD-Foundation3/16/20013/16/20013/16/2001 12:00:00 AMPPASS
###-####
BLD01-00518 BLD-Footing3/16/20013/16/20013/16/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 03/16/2001 at 09:01:34. Contact: wip appears ok 3/16/2001 2:59:25 PM
BLD01-00549 BLD-Footing3/16/20013/16/20013/16/2001 12:00:00 AMPNR
###-#### JACK wip 3/16/2001 1:51:20 PM
BLD01-00003 BLD-Framing/Rough-in3/15/20013/16/20013/16/2001 12:00:00 AMPCANC
###-#### Already been completed. 3/16/2001 1:35:31 PM
BLD01-00298 BLD-Framing/Rough-in3/13/20013/16/20013/16/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 03/13/2001 at 17:01:32. Contact: ###-####. Shear--ok to side. 3/16/2001 2:10:55 PM