FIR08-00725
| INSP-Final Inspection | 3/16/2009 | 3/16/2009 | 3/16/2009 5:33:12 PM | P | PASS |
|
|
Noted correction items field verified for completion, fire alarm testing passed, permit finaled.
|
FIR08-00766
| INSP-Sprinkler Rough-in/Hydro | 3/13/2009 | 3/16/2009 | 3/16/2009 5:31:23 PM | P | PART |
|
|
UG fire supply line hydrostatic testing for the lead in to the pump house and the supply/feed to the west half of the building including three stubs passed within allowable leakage amounts per NFPA 13.
|
FIR08-00018
| INSP-Sprinkler Rough-in/Hydro | 3/13/2009 | 3/16/2009 | 3/16/2009 5:27:23 PM | A | FAIL |
|
|
Rough-in inspection for the 12th floor failed due to head spacing at six locations in need of adjustment between upright and sidewall heads, see red-line notes on plans.
|
BLD08-00703
| FIRE-Final Inspection | 3/13/2009 | 3/16/2009 | 3/16/2009 5:25:22 PM | A | FAIL |
|
|
Need to adjust closure at the east side pair of elevator lobby doors, provide approved hardware at both stairway exit doors. EM lighting and exit signs tested okay.
|