Inspections for the day of: Monday, March 16, 2009.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00725 INSP-Final Inspection3/16/20093/16/20093/16/2009 5:33:12 PMPPASS
Noted correction items field verified for completion, fire alarm testing passed, permit finaled.
FIR08-00766 INSP-Sprinkler Rough-in/Hydro3/13/20093/16/20093/16/2009 5:31:23 PMPPART
UG fire supply line hydrostatic testing for the lead in to the pump house and the supply/feed to the west half of the building including three stubs passed within allowable leakage amounts per NFPA 13.
FIR08-00018 INSP-Sprinkler Rough-in/Hydro3/13/20093/16/20093/16/2009 5:27:23 PMAFAIL
Rough-in inspection for the 12th floor failed due to head spacing at six locations in need of adjustment between upright and sidewall heads, see red-line notes on plans.
BLD08-00703 FIRE-Final Inspection3/13/20093/16/20093/16/2009 5:25:22 PMAFAIL
Need to adjust closure at the east side pair of elevator lobby doors, provide approved hardware at both stairway exit doors. EM lighting and exit signs tested okay.