Inspections for the day of:
Monday, March 16, 2009
.
Number of inspections:
14
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Clint A Smith
Title
EROSION CONTROL INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC07-00987
Random Inspection
3/16/2009
3/16/2009
3/16/2009 5:44:34 PM
P
FAIL
Verbal to RP:
1. Clean up all trash debris and place into a proper trash container.
2. Clean up all conrete spoil piles and place into the wahout that is provided.
3. Maintain storm drains since 50% capcity has been reached.
Will re-inspect on 3/19/09 AM.
ESC09-00085
Site Preparation ESC
3/16/2009
3/16/2009
3/16/2009 3:14:58 PM
FAIL
Verbal to RP:
Post ESC sign at the front of project.
Protet storm drain to the west of project area in the court.
Will re-inspect on 3/19/09AM.
ESC09-00061
Site Preparation
3/16/2009
3/16/2009
3/16/2009 3:08:11 PM
PASS
ESC08-00820
Complaint Inspection
3/16/2009
3/16/2009
3/16/2009 3:04:39 PM
P
FAIL
Verbal to RP:
Need to install perimeter protection on front of the unfinished driveway.
ESC09-00110
Site Preparation
3/16/2009
3/16/2009
3/16/2009 3:01:14 PM
PASS
ESC08-00638
General Inspection
3/16/2009
3/16/2009
3/16/2009 2:59:12 PM
PASS
ESC08-00491
General Inspection
3/9/2009
3/16/2009
3/16/2009 11:35:06 AM
A
FAIL
Verbal to RP:
Still need to address access point at Winco Ct. Will be doing so since work will be starting on the curb cut today.
ESC08-00750
General Inspection
3/12/2009
3/16/2009
3/16/2009 10:40:02 AM
A
PASS
ESC08-00763
General Inspection
3/12/2009
3/16/2009
3/16/2009 10:39:37 AM
A
PASS
ESC08-00736
BMP Violation
3/12/2009
3/16/2009
3/16/2009 10:39:03 AM
A
PART
all issues taken care of. Just need to pick up excess wood that is on the the sidewalk.
ESC08-01050
Site Preparation
3/16/2009
3/16/2009
3/16/2009 9:45:57 AM
FAIL
Verbal to RP:
1.Post ESC sign at the front entrance of project.
2. Install all sediment barriers perindustry standards.
3. Widen and lengthen the construction access.
4. Clean up all tracking off of construction access.
Will re-inspect on 3/18/09 AM.
ESC08-00866
BMP Violation
3/16/2009
3/16/2009
3/16/2009 8:46:49 AM
A
FAIL
Verbal to RP:
Clean up all sediment and debris off of all hard surfaces. Mo stock pile off of hard surfaces onto the drive way and install a sediment barrier at the edge of drive way.
Will be removing stock pile along the edge of drainiage basin starting today. Will re-inspect on 3/18/09 AM.
ESC08-00577
General Inspection
3/16/2009
3/16/2009
3/16/2009 8:28:58 AM
PART
Site looks good. All bmps working correctly. Told RP to clean up the trash debris scattered along the hill sides.
ESC06-01177
Site Final
3/15/2009
3/16/2009
3/15/2009 5:52:40 PM
A
PASS