Inspections for the day of: Friday, March 16, 2018.
Number of inspections: 31
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBrian Scoles
TitleMEC INSPECTOR
Phone #914-4915
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC18-01205 Rough-in3/16/20183/16/20183/16/2018 4:16:55 PMPPASS
fp r/i and p/t - Oleg Phone #: ###-####- fireplace and R/I ok- Gas was witnessed early today
MEC18-00997 Rough-in3/15/20183/16/20183/16/2018 3:57:38 PMPPASS
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- R/I ok
MEC18-00997 Pressure Test3/15/20183/16/20183/16/2018 3:57:17 PMPPASS
Phone #: ###-#### Inspection requested via web by dannyel chaloupka- 20lb gas pass
MEC18-01207 Final3/16/20183/16/20183/16/2018 3:56:56 PMPPASS
Inspection requested via web by Floyd Floyd Peek- furnace ac coil co ok
MEC18-01071 Rough-in3/16/20183/16/20183/16/2018 3:49:57 PMPPASS
Phone #: ###-#### Inspection requested via web by Philip Yates- fireplace R/I ok
MEC18-01189 Pressure Test3/15/20183/16/20183/16/2018 3:29:43 PMPPASS
Phone #: ###-#### Inspection requested via web by Krista Boss- furnace coil ac co ok
MEC17-00199 Final3/15/20183/16/20183/16/2018 3:19:18 PMPPASS
Our technician will be onsite from 2 pm - 4 pm. Please call on way. Ethan ###-####. Phone #: ###-#### Inspection requested via web by Krista Boss- funace coil ac co ok
MEC18-01142 Final3/16/20183/16/20183/16/2018 3:10:15 PMPPASS
ready, please call Chris ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- furnace coil ac ok
MEC18-01209 Final3/16/20183/16/20183/16/2018 2:46:16 PMPPASS
Inspection requested via web by Floyd Floyd Peek- furnace coil ac co ok
MEC18-01191 Pressure Test3/16/20183/16/20183/16/2018 2:40:14 PMPPASS
Oleg Phone #: ###-####- R/I ok- Fireplace R/I ok
MEC18-00894 Rough-in3/16/20183/16/20183/16/2018 1:21:29 PMPPART
Inspection requested via web by Ashley Stegemann- fireplace R/I will pass when all permits are attached to right address
MEC18-01220 Rough-in3/16/20183/16/20183/16/2018 1:20:55 PMPPART
Inspection requested via web by Ashley Stegemann- fireplace R/I will pass when all permits are attached to right address
MEC18-01201 Rough-in3/16/20183/16/20183/16/2018 1:20:02 PMPFAIL
Inspection requested via web by Ashley Stegemann- plastic at floor is touching the fireplace- plastic needs secured better-
MEC18-00674 Rough-in3/16/20183/16/20183/16/2018 1:19:02 PMPPART
Daniel promises it is ready ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- R/I will pass for cover when all permits have been attached to right address
MEC18-01107 Rough-in3/16/20183/16/20183/16/2018 11:36:23 AMAPASS
Phone #: ###-#### Inspection requested via web by Randy Hart- fireplace R/I ok
MEC18-01155 Rough-in3/15/20183/16/20183/16/2018 11:04:17 AMAPASS
Phone #: ###-#### Inspection requested via web by Devony Bullard- R/I ok
MEC18-01155 Pressure Test3/15/20183/16/20183/16/2018 11:03:41 AMAPASS
Phone #: ###-#### Inspection requested via web by Devony Bullard- 20lb gas pass
MEC18-01154 Rough-in3/15/20183/16/20183/16/2018 10:47:35 AMAPASS
Phone #: ###-#### Inspection requested via web by Devony Bullard- R/I ok
MEC18-01154 Pressure Test3/15/20183/16/20183/16/2018 10:47:19 AMAPASS
Phone #: ###-#### Inspection requested via web by Devony Bullard- 20lb gas pass
MEC18-00543 Final3/15/20183/16/20183/16/2018 10:06:00 AMANR
Phone #: ###-#### Inspection requested via web by Randy Hart- tile still being installed- need gas and face plate installed to final out
MEC18-00542 Conference3/15/20183/16/20183/16/2018 10:05:10 AMAPASS
Blast witness 930am please Phone #: ###-#### Inspection requested via web by Randy Hart- duct blast test pass
MEC18-00542 Final3/15/20183/16/20183/16/2018 10:02:10 AMAPASS
Blast witness 930am please Phone #: ###-#### Inspection requested via web by Randy Hart
MEC18-00732 Rough-in3/16/20183/16/20183/16/2018 10:00:38 AMPCANC
>> Inspection requested via web by Ashley Stegemann Inspection cancelled from web by: Ashley Stegemann
MEC18-01110 Rough-in3/15/20183/16/20183/16/2018 9:45:10 AMAPASS
re-inspect for rough Phone #: ###-#### Inspection requested via web by Brandon Sorensen- R/I ok
MEC18-00888 Final3/14/20183/16/20183/16/2018 9:26:06 AMAPASS
PAT ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza- Final ok- co installed
MEC18-00888 Rough-in3/14/20183/16/20183/16/2018 9:25:44 AMAPASS
PAT ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza- R/I ok
MEC17-01723 Mec-Aging Inspection3/16/20183/16/20183/16/2018 9:11:53 AM PEND
contractor will try and schedule final per phone call
MEC18-01191 Rough-in3/15/20183/16/20183/16/2018 8:55:52 AMAFAIL
FIREPL Phone #: ###-#### Inspection requested via web by Oleg Chervak- fireplace metal firestop upside down inside of house- talk with Oleg about this-
MEC18-01205 Rough-in3/15/20183/16/20183/16/2018 8:37:26 AMAFAIL
MEC AND FIREPL Phone #: ###-#### Inspection requested via web by Oleg Chervak- HVAC R/I ok- fireplace R/I failed- metal firestop on inside is upside down and plastic will need secured- does not have 3" clearance on top per insttall instructions
MEC18-01205 Pressure Test3/15/20183/16/20183/16/2018 8:35:29 AMAPASS
Phone #: ###-#### Inspection requested via web by Oleg Chervak- 20lb gas pass
MEC18-01056 Rough-in3/15/20183/16/20183/16/2018 8:18:55 AMAPASS
Inspection requested via web by Ashley Stegemann- fireplace R/I ok- no gas test needed