Inspections for the day of: Monday, March 16, 2020.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBrian Scoles
TitleMEC INSPECTOR
Phone #914-4915
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-05816 Final3/16/20203/16/20203/16/2020 3:39:20 PMPPASS
please call with any questions or concerns. Thank you Jennifer Phone #: ###-#### Inspection requested via web by ted roy- final ok
MEC20-01066 Rough-in3/13/20203/16/20203/16/2020 3:12:01 PMPPASS
Inspection requested via web by Jenny Telford- R/I 2 bath fans ok- ok to cover above floor to ceiling only- need other mechanical permit issued for rest of R/I inspection
MEC20-01073 Pressure Test3/13/20203/16/20203/16/2020 2:40:05 PMPPASS
Please inspect early PM and cal chuck on your way - ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks- 20lb gas pass from meter thru garage outside back of house and into furnace room and up to range- sectioned tested not tied into meter at time of test- co ok
MEC20-01072 Final3/16/20203/16/20203/16/2020 1:51:12 PMPPASS
final ok- card signed
MEC20-01072 Rough-in3/13/20203/16/20203/16/2020 1:50:26 PMPPASS
Please call in advance so that I can plan to have the suite unlocked. Phone #: ###-#### Inspection requested via web by Joey Hickman- R/I on1 future exhaust duct in wall only ok to cover- 1 supply register relocated to center of room 1 place only- no other Mechaincal at this time on this permit
MEC19-05181 Final3/16/20203/16/20203/16/2020 1:15:34 PMPFAIL
Phone #: ###-#### Inspection requested via web by Randy Hart- final will pass when 1 exhaust fan and 1 range added to permit and fee payed- recall in when ready and lll final out
MEC20-00959 Final3/16/20203/16/20203/16/2020 12:56:10 PMPPASS
final ok
MEC20-00959 Pressure Test3/9/20203/16/20203/16/2020 12:55:20 PMPPASS
PLEASE CALL WHEN ON THE WAY. THANK YOU Phone #: ###-#### Inspection requested via web by SARA GREENHALGH- 20lb gas pass
MEC20-00892 Rough-in3/16/20203/16/20203/16/2020 11:33:32 AMANR
C/I for today. Please contact Robbie prior to arrival. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
1- need to add 3 dryer ducts and 2 bath fans to permit and pay fee
2- all framing around linesets, fresh air for fireplaces and dryer ducts need completed for R/I inspection
3- 4 dryer vents ok
4- range duct ok
5- linesets and drains for mini splits ok

recall in when ready
MEC20-01030 Final3/11/20203/16/20203/16/2020 9:52:22 AMPCANC
INSTALLER DAKOTA ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- schedule for wrong day per phone call with Dustin
MEC20-00890 Final3/13/20203/16/20203/16/2020 9:38:38 AMAPASS
Please inspect from 9-11 if possible. Homeowner Ray Toland ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette- a/c coil co locking caps ok
MEC20-00839 Rough-in3/13/20203/16/20203/16/2020 9:10:03 AMADONE
Meeting on site with builder/contractor 10:00am Phone #: ###-#### Inspection requested via web by David Nelson- meet to discuss med gas room on shaft and ducting will require plan mod and engineers approved drawings
MEC20-00839 Rough-in3/16/20203/16/20203/16/2020 9:09:19 AMAPART
Meeting on site with builder/contractor 10:00am Phone #: ###-#### Inspection requested via web by David Nelson- ok to cover excluding med gas room- will need plan mod approved for routing of ducting
MEC20-01067 Final3/12/20203/16/20203/13/2020 3:54:29 PMACANC
KAREN ###-#### - CALL FOR ACCESS Phone #: ###-#### >> Inspection requested via web by Mike Almanza Inspection cancelled from web by: Mike Almanza
MEC20-01073 Final3/13/20203/16/20203/13/2020 2:58:56 PMACANC
Please inspect Later AM and call Chuck on your way - ###-#### Phone #: ###-#### >> Inspection requested via web by Arielle Hendricks Inspection cancelled from web by: Arielle Hendricks