ELE05-03668
| ELE-Aging Inspection | 3/17/2006 | 3/17/2006 | 3/20/2006 11:46:51 AM | | PART |
|
|
called waiting for info from contractor
|
ELE05-03958
| ELE-Aging Inspection | 3/17/2006 | 3/17/2006 | 3/17/2006 4:19:21 PM | | PART |
|
|
called cotractor he will follow up and schedule final inspection when ready
|
ELE05-04023
| Final | 3/17/2006 | 3/17/2006 | 3/17/2006 4:13:08 PM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 3/17/2006 at 9:04:28 AM. Contact: ###-####. contractor made correction,surfsce extension from jbox entela testing field evaluation ok all equipment passed and labeled, card signed
|
ELE06-00863
| Temporary Service | 3/17/2006 | 3/17/2006 | 3/17/2006 3:37:20 PM | P | PASS |
|
|
Rhonda ###-####; reinspect because changed from underground to overhead per Idaho Power requirements; okay for reinspection per Jack Frank as stated by Rhonda (Falcon Electric) t/s o/h new ok jf changed from u/g to o/h
|
ELE06-00881
| Rough-In Permanent Service | 3/17/2006 | 3/17/2006 | 3/17/2006 3:13:47 PM | P | PASS |
|
|
house is locked you need to call ###-#### 30 min. prior for access; Phone #: ###-#### Internet Inspection Request from: joe wheeler corrections made permit updated to 5 rms r/i ok p/s o/h rec. ok
|
ELE05-04417
| Electrical Rough-In | 3/17/2006 | 3/17/2006 | 3/17/2006 2:25:27 PM | P | PART |
|
|
Scheduled by a contractor via Hello! on 3/17/2006 at 7:15:24 AM. u/g for pole lights and PIV valve front and back lots
|
ELE05-04151
| Final | 3/17/2006 | 3/17/2006 | 3/17/2006 1:40:29 PM | P | PASS |
|
|
Rick; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ok
|
ELE05-03886
| Final | 3/16/2006 | 3/17/2006 | 3/17/2006 12:57:37 PM | A | CANC |
|
|
Phone #: ###-#### Internet Inspection Request from: Kathy Briggs see added conf.
|
ELE05-03886
| Conference | 3/17/2006 | 3/17/2006 | 3/17/2006 12:57:08 PM | P | DONE |
|
|
Phone #: ###-#### Internet Inspection Request from: Kathy Briggs met with Bob R and contractor we disccussed the violations Bob posted and contractor did not correct
|
ELE05-04071
| Conference | 3/17/2006 | 3/17/2006 | 3/17/2006 12:09:34 PM | A | DONE |
|
|
per jack for conf ok
|
ELE06-00586
| Final | 3/10/2006 | 3/17/2006 | 3/17/2006 10:46:02 AM | A | NH |
|
|
We wired a new 30 amp 3 wire circuit to a new box below the panel. The home owner is installing his own receptacle om this circuit.Thanks!!! Dan.; Phone #: notice posted called
|
ELE06-00858
| Final | 3/16/2006 | 3/17/2006 | 3/17/2006 10:03:05 AM | A | PASS |
|
|
CALL MILES TO MEET @ ###-####. INSPECT HOT TUB . THANK YOU.; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH
|
ELE06-00738
| Final | 3/16/2006 | 3/17/2006 | 3/17/2006 9:20:01 AM | A | PASS |
|
|
NEED FINAL ON FURNACE INSTALL.; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH ok
|
ELE06-00881
| Rough-In Permanent Service | 3/16/2006 | 3/17/2006 | 3/17/2006 8:49:43 AM | A | FAIL |
|
|
Phone #: ###-#### Internet Inspection Request from: joe wheeler corr. do not cover, and fee due posted needs to update permit to 5 rooms called 300.4 (A)(1)(D) nail plates and 11/4" everywhere, 110.3(A&B) GEC shall terminate into one terminal only at p/s, 210.52(A,B,C) nedds outlet wall new wall space kit, also countertop spacing over 4ft between recepts, 250.24(A)(1) all water grds and bonds shall terminate at service not subpanel bond hot and cold where is it?
|