Inspections for the day of: Friday, March 17, 2006.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00025 INSP-Final Inspection3/16/20063/17/20063/24/2006 3:00:05 PMPDEFR
To be rescheduled.
FIR05-00594 INSP-Sprinkler Rough-in3/16/20063/17/20063/17/2006 3:41:49 PMPPART
Third and fourth floor overhead rough-in is acceptable for cover.
FIR06-00154 INSP-Final Inspection3/16/20063/17/20063/17/2006 2:55:12 PMAPART
Hood suppression system functioned properly under test conditions, flame separation between fryer and range is not yet provided, need to install K class extinguisher.
FIR06-00038 INSP-Final Inspection3/16/20063/17/20063/17/2006 2:34:44 PMAFAIL
Various locations are overspaced beyond the maximum design area/density of 148 ft2, overspaced locations are marked on approved plans, one room marked as "file room" shall be spaced for ordinary hazard.
FIR05-00575 INSP-Alarm Testing3/16/20063/17/20063/17/2006 1:34:51 PMAPART
Per state elevator requirements, the top of shaft will require a heat detector, need to test elevator lobby SD 3rd floor north and smoke and heat in top of shaft, outside bell repaired while on site, panel, sprinkler, notification, alarm, supervision, trouble and EOL tested okay, provide signal verification as discussed, provide as-builts and updated map at next inspection, provide signage at the door to the FACP.
FIR05-00273 INSP-Final Inspection3/16/20063/17/20063/17/2006 1:24:59 PMAPART
Items on previous correction notice have been completed, per state elevator requirements the wood framed sheetrocked shaft is considered combustible and will require a sprinkler at the top.
BLD04-00944 FIRE-Final Inspection3/16/20063/17/20063/17/2006 1:11:23 PMAFAIL
Fire extinguishers are not installed, curb painting is not complete, door hardware in some locations is not installed, fire alarm and sprinkler permits must be finaled prior to life safety final, project life safety not ready for inspection at this time.
FIR05-00888 INSP-Final Inspection3/15/20063/17/20063/17/2006 12:59:45 PMAPART
Fire alarm work tested satisfactory, final pending completion of the related shell alarm permit.
FIR05-00889 INSP-Final Inspection3/15/20063/17/20063/17/2006 12:58:32 PMAFAIL
Insufficient visual coverage at the "work area" as indicated on plans, duct detector and pull stations tested okay.
BLD05-03176 FIRE-Final Inspection3/16/20063/17/20063/17/2006 11:24:43 AMAPART
Temporary occupancy approval pending building structural inspection. Fire final pending verification of fire sprinkler plan resubmittals.
FIR06-00037 INSP-Final Inspection3/16/20063/17/20063/17/2006 10:15:46 AMAPART
Verified forward flow, PIV tamper has been disconnected from outside water flow bell as discussed, final pending plan resubmittals as required.