BLD08-02393
| FIRE-Conference | 3/17/2009 | 3/17/2009 | 3/17/2009 11:28:57 AM | P | DONE |
|
|
I spoke to Brian Johnson with Shilo Automatic Sprinkler about the sizing of the piping from the FDC to the floating main. I gave my interpretation of NFPA 13-8.17.2 but defered him to Tim Frost. The entry is being made under this permit due to the overhead sprinkler permit not being issued at this time.
|
BLD07-02085
| FIRE-Sprinkler Rough-in | 3/17/2009 | 3/17/2009 | 3/17/2009 11:26:41 AM | P | PASS |
|
|
A sprinkler inspection was performed on the attic dry system for Building B. The attic system in building B can be covered. See the city approved plans, FIR08-00831, for the specific area. The inspection report is being made under the building permit due to the sprinkler permit being in the review status for wet system changes requiring resubmittals.
|
BLD07-02085
| FIRE-Sprinkler Rough-in | 3/17/2009 | 3/17/2009 | 3/17/2009 11:26:26 AM | A | PASS |
|
|
A sprinkler inspection was performed on the attic dry system for Building B. See the city approved sprinkler plans for locations where three sprinkler heads need to be added. The inspection report is being made under the building permit due to the sprinkler permit being in the review status for wet system changes requiring resubmittals.
|
FIR09-00161
| INSP-Sprinkler Rough-in/Hydro | 3/17/2009 | 3/17/2009 | 3/17/2009 10:52:00 AM | P | PASS |
|
|
The remaining sprinkler piping is ok to cover.
|
FIR07-00874
| INSP-Sprinkler Rough-in/Hydro | 3/16/2009 | 3/17/2009 | 3/17/2009 10:20:52 AM | A | PASS |
|
|
Above ground hydro test for ALF canopy on the south side of the building passed.
|
BLD09-00260
| FIRE-Final Inspection | 3/16/2009 | 3/17/2009 | 3/17/2009 9:56:37 AM | A | FAIL |
|
|
No access into the tenant.
|
FIR09-00134
| INSP-Final Inspection | 3/16/2009 | 3/17/2009 | 3/17/2009 9:18:55 AM | A | PASS |
|
|
Permit finaled
|