Inspections for the day of: Thursday, March 17, 2016.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00602 INSP-Sprinkler Rough-in3/17/20163/17/20163/17/2016 3:20:39 PMPCANC
Inspection request cancelled per conversation with Bryan, concrete would not be delivered before end of business day, contractor will reschedule inspection request.
FIR15-00698 INSP-Sprinkler Rough-in3/17/20163/17/20163/17/2016 2:08:46 PMPPASS
Rough in inspection complete for office area's located on mezzanine as well as elevated storage tanks located in the warehouse.
BLD16-00204 FIRE-Final Inspection3/16/20163/17/20163/17/2016 11:47:26 AMAPASS
All previously noted items repaired, final life fire safety inspection passed/complete
BLD15-04417 FIRE-Final Inspection3/16/20163/17/20163/17/2016 11:31:28 AMAPART
Project is being divided into phases, fire sprinklers for phase one area complete, fire alarms will be tested when area of work is completed, fire extinguishers are in place for phase one area with current inspection tags. Life fire safety inspection passed/complete for phase 1 area.
FIR16-00047 INSP-Final Inspection3/17/20163/17/20163/17/2016 11:28:51 AMPPASS
Final fire sprinkler inspection passed/complete
FIR15-00885 INSP-Final Inspection3/17/20163/17/20163/17/2016 11:24:03 AMPPART
Project being worked in phases, inspected fire sprinkler system in area being labeled as phase 1, area inspected passed/complete for final inspection. Inspection will be schedule at a later date for phase 2 area.
BLD15-04406 FIRE-Final Inspection3/16/20163/17/20163/17/2016 11:20:31 AMACANC
Final inspection cancelled per conversation with Greg Phone #: ###-####, will reschedule inspection to coincide with FIR permit final inspections.
FIR13-00312 INSP-Sprinkler Rough-in/Hydro3/17/20163/17/20163/17/2016 10:46:54 AMAPASS
Audio/visuals tested for first level, all A/V devices inspected passed operational and visual inspection. A/V testing complete for this scope of work.
FIR16-00151 INSP-Final Inspection3/17/20163/17/20163/17/2016 10:42:37 AMAPASS
Final fire alarm inspection passed/complete
BLD16-00551 FIRE-Final Inspection3/16/20163/17/20163/17/2016 9:38:40 AMAPASS
No fire sprinkler modifications, no fire alarms, fire extinguishers have current inspection tags. Life fire safety inspection passed/complete.
FIR15-00794 INSP-Final Inspection3/16/20163/17/20163/17/2016 9:09:39 AMACANC
Inspection request cancelled per conversation with point of contatct, Morgan Phone #: ###-####, contractor will reschedule inspection for later date.