FIR15-00602
| INSP-Sprinkler Rough-in | 3/17/2016 | 3/17/2016 | 3/17/2016 3:20:39 PM | P | CANC |
|
|
Inspection request cancelled per conversation with Bryan, concrete would not be delivered before end of business day, contractor will reschedule inspection request.
|
FIR15-00698
| INSP-Sprinkler Rough-in | 3/17/2016 | 3/17/2016 | 3/17/2016 2:08:46 PM | P | PASS |
|
|
Rough in inspection complete for office area's located on mezzanine as well as elevated storage tanks located in the warehouse.
|
BLD16-00204
| FIRE-Final Inspection | 3/16/2016 | 3/17/2016 | 3/17/2016 11:47:26 AM | A | PASS |
|
|
All previously noted items repaired, final life fire safety inspection passed/complete
|
BLD15-04417
| FIRE-Final Inspection | 3/16/2016 | 3/17/2016 | 3/17/2016 11:31:28 AM | A | PART |
|
|
Project is being divided into phases, fire sprinklers for phase one area complete, fire alarms will be tested when area of work is completed, fire extinguishers are in place for phase one area with current inspection tags. Life fire safety inspection passed/complete for phase 1 area.
|
FIR16-00047
| INSP-Final Inspection | 3/17/2016 | 3/17/2016 | 3/17/2016 11:28:51 AM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
FIR15-00885
| INSP-Final Inspection | 3/17/2016 | 3/17/2016 | 3/17/2016 11:24:03 AM | P | PART |
|
|
Project being worked in phases, inspected fire sprinkler system in area being labeled as phase 1, area inspected passed/complete for final inspection. Inspection will be schedule at a later date for phase 2 area.
|
BLD15-04406
| FIRE-Final Inspection | 3/16/2016 | 3/17/2016 | 3/17/2016 11:20:31 AM | A | CANC |
|
|
Final inspection cancelled per conversation with Greg Phone #: ###-####, will reschedule inspection to coincide with FIR permit final inspections.
|
FIR13-00312
| INSP-Sprinkler Rough-in/Hydro | 3/17/2016 | 3/17/2016 | 3/17/2016 10:46:54 AM | A | PASS |
|
|
Audio/visuals tested for first level, all A/V devices inspected passed operational and visual inspection. A/V testing complete for this scope of work.
|
FIR16-00151
| INSP-Final Inspection | 3/17/2016 | 3/17/2016 | 3/17/2016 10:42:37 AM | A | PASS |
|
|
Final fire alarm inspection passed/complete
|
BLD16-00551
| FIRE-Final Inspection | 3/16/2016 | 3/17/2016 | 3/17/2016 9:38:40 AM | A | PASS |
|
|
No fire sprinkler modifications, no fire alarms, fire extinguishers have current inspection tags. Life fire safety inspection passed/complete.
|
FIR15-00794
| INSP-Final Inspection | 3/16/2016 | 3/17/2016 | 3/17/2016 9:09:39 AM | A | CANC |
|
|
Inspection request cancelled per conversation with point of contatct, Morgan Phone #: ###-####, contractor will reschedule inspection for later date.
|