BLD15-04468
| BLD-Conference | 3/16/2017 | 3/17/2017 | 3/17/2017 5:19:07 PM | P | PASS |
|
|
Friday walk to review status. Call Adam When on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD16-03443
| BLD-Framing/Rough-in | 3/17/2017 | 3/17/2017 | 3/17/2017 5:18:56 PM | P | PART |
|
|
would like call ahead; Sam Phone #: ###-#### insulation is ok but still missing two hold downs or strapes second floor wall over mec in garage
|
BLD16-03443
| BLD-Energy code compliance | 3/17/2017 | 3/17/2017 | 3/17/2017 5:18:38 PM | P | PEND |
|
|
would like call ahead; Sam Phone #: ###-#### insulation is ok but still missing two hold downs or strapes second floor wall over mec in garage
|
BLD16-04339
| BLD-Framing/Rough-in | 3/17/2017 | 3/17/2017 | 3/17/2017 5:16:26 PM | P | PART |
|
|
Rusty Phone #: ###-#### ok to insulate but needs calcs on 14 inch lvls
|
BLD16-03645
| BLD-Framing/Rough-in | 3/17/2017 | 3/17/2017 | 3/17/2017 2:45:56 PM | P | FAIL |
|
|
Plans/ engineering at garage Inspection requested via web by Erby Gonzales air seal done no inspection done
|
BLD16-03247
| BLD-Final | 3/16/2017 | 3/17/2017 | 3/17/2017 2:03:42 PM | A | PASS |
|
|
would like call ahead Phone #: ###-####
|
BLD17-00098
| BLD-Foundation | 3/16/2017 | 3/17/2017 | 3/17/2017 11:59:36 AM | A | PASS |
|
|
Adam Phone #: ###-####
|
BLD17-00385
| BLD-Final | 3/16/2017 | 3/17/2017 | 3/17/2017 11:59:23 AM | A | PASS |
|
|
Solar Array. Please call and let me know if you need us to meet you onsite with our approved plans. Everything was installed exactly as planned. Phone #: ###-#### Inspection requested via web by Matthew Dunay
|
BLD17-00385
| DOC - Permit Finaled | 3/17/2017 | 3/17/2017 | 3/17/2017 11:59:14 AM | P | PASS |
|
|
|
BLD16-03359
| BLD-Framing/Rough-in | 3/16/2017 | 3/17/2017 | 3/17/2017 9:30:36 AM | A | PASS |
|
|
Building 4 // Terry Phone #: ###-####
|
BLD15-03329
| BLD-Framing/Rough-in | 3/16/2017 | 3/17/2017 | 3/17/2017 9:14:52 AM | A | PEND |
|
|
Trash Chute Walls Phone #: ###-#### Inspection requested via web by Ami Tracy ok to cover all but for sixth floor shaft does not up though attic must cut attic trusses to get shaft though roof
|
BLD16-03292
| BLD-Foundation | 3/16/2017 | 3/17/2017 | 3/17/2017 9:12:23 AM | A | PASS |
|
|
Rebar // Rob Phone #: ###-####
|