PLM03-00687
| Plumbing Rough-in | 3/17/2003 | 3/18/2003 | 3/18/2003 12:00:00 AM | P | PART |
|
|
BUSS MECH UNDER GRID INSPECTION; Phone #: ###-#### Internet Inspection Request from: Darla Downs gw ok with trap primers on the floor drains 3/18/2003 3:02:22 PM
|
PLM03-00692
| Plumbing Rough-in | 3/18/2003 | 3/18/2003 | 3/18/2003 12:00:00 AM | P | PASS |
|
|
###-#### jan (ready anytime) ri ok 3/18/2003 11:17:38 AM
|
PLM02-03818
| Final | 3/18/2003 | 3/18/2003 | 3/18/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 3/18/2003 at 11:21:53 AM. Contact: ###-####. final ok, david said he was taking responsibility for the water softeror installed by san ray plumbing. 3/18/2003 2:20:08 PM
|