Inspections for the day of: Wednesday, March 18, 2009.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00018 INSP-Sprinkler Rough-in/Hydro3/16/20093/18/20093/18/2009 5:05:10 PMPPART
2 hr Hydro - Contact: Jeff
Rough In Inspection Phone #: ###-#### Internet Inspection Request from: Alicia Pauley NOTE: See comments per T. Frost
FIR09-00106 INSP-Sprinkler Rough-in3/18/20093/18/20093/18/2009 4:58:32 PMPPART
Overhead rough-in appears satisfactory, final pending new approved plans reflecting field modifications to indicate added heads, relocated heads, and new QR heads installed within the tenant remodel.
FIR08-00818 FIR-Aging Inspection3/18/20093/18/20093/18/2009 4:52:50 PM NR
Pending site inspection request.
FIR08-00766 INSP-Supply line flush3/16/20093/18/20093/18/2009 4:51:12 PMAPART
UG flush completed satisfactory for the two far west system lead-ins, ( main supply line and the west main supply line included).
FIR08-00728 INSP-Alarm Testing3/18/20093/18/20093/18/2009 4:44:32 PMAPART
Fire alarm testing completed today includes the new FACP, nac extenders, notification, initiation, and sprinkler monitoring for the main building.
FIR08-00699 INSP-Sprinkler Rough-in3/17/20093/18/20093/18/2009 4:41:11 PMAPART
See plans marked for rough-in inspection completed today including three seismic braces to be added as discussed.