Inspections for the day of: Tuesday, March 18, 2014.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00081 INSP-Final Inspection3/18/20143/18/20143/20/2014 10:55:37 AMPPASS
Hood suppression systems operated correctly under test conditions. Permit finaled.
FIR13-00252 INSP-Final Inspection3/17/20143/18/20143/20/2014 10:53:11 AMPPASS
Fire sprinkler permit finaled.
FIR13-00648 INSP-Final Inspection3/12/20143/18/20143/18/2014 3:07:04 PMPPART
Completed fire alarm acceptance testing. Necessary adjustments made while on site. Scope of work completed. Final pending installation of a knox box per review note item #13.
BLD13-02108 FIRE-Final Inspection3/17/20143/18/20143/18/2014 2:32:28 PMPPASS
Fire life safety inspection completed. Need to add identification labels at refrigerant alarms, noted two fire extingusihers at the basement level overdue annual certification. To be completed prior to structural final.
BLD14-00168 FIRE-Final Inspection3/17/20143/18/20143/18/2014 2:29:36 PMADONE
david or jessie at ###-#### Phone #: ###-####
FIR13-00713 INSP-Sprinkler Rough-in3/17/20143/18/20143/18/2014 11:29:52 AMAFAIL
First floor corrections include; missing hangers at two locations, piping to SW heads incompleted, provide intermediate temp heads at the furnace closets, min. distance between heads is not met at two units, a swing joint at the west end unit appears to be "dry fit".
FIR14-00081 INSP-Final Inspection3/17/20143/18/20143/18/2014 10:50:29 AMANR
dave Phone #: ###-#### * Equipment not ready for testing at this time- Inspection to be rescheduled.
FIR14-00124 INSP-Sprinkler Rough-in3/17/20143/18/20143/18/2014 9:45:16 AMAPART
Fire sprinkler work at the mens and womens restroom, utility, hallway and cooler approved for cover as marked/dated on approved plan set.