FIR14-00722
| INSP-Alarm Testing | 3/18/2015 | 3/18/2015 | 3/18/2015 3:33:38 PM | P | DONE |
|
|
Todays inspection was only to verify horn/strobe function. All audio/visuals operated correctly.
|
FIR15-00082
| INSP-Sprinkler Rough-in | 3/18/2015 | 3/18/2015 | 3/18/2015 2:54:19 PM | P | PASS |
|
|
See the city approved plans for Womens Restroom, first floor, where piping is ok to cover as marked "ok" on the city approved plans.
|
FIR14-00475
| INSP-Sprinkler Rough-in/Hydro | 3/18/2015 | 3/18/2015 | 3/18/2015 2:52:24 PM | P | PART |
|
|
Revised plans provided but one piece of pipe installed in the remote area does not match the city approved plans. Also verification needs to be provided for the exposed 2" cpvc pipe can remain exposed. Piping can be covered except for the piping in the remote area until sizing is settled through plan review or changed to match the approved drawings.
|
FIR15-00081
| INSP-Alarm Testing | 3/17/2015 | 3/18/2015 | 3/18/2015 2:49:10 PM | P | FAIL |
|
|
Provide shielded wire, relocate smoke detector to within 12" of deck, provide orfice for inspectors test, provide document box and provide testing of devices.
|
BLD14-02689
| FIRE-Final Inspection | 3/17/2015 | 3/18/2015 | 3/18/2015 12:33:15 PM | A | PART |
|
|
East most phase of project life safety is passed. New emergency light installed as well as ceiling tile and fire extinguisher. Waiting on single action hardware for exterior exit doors
|
FIR14-00602
| INSP-Supply line flush | 3/16/2015 | 3/18/2015 | 3/18/2015 9:28:57 AM | A | PASS |
|
|
Underground flush and forward flush test passed inspection
|
BLD14-01856
| FIRE-Conference | 3/17/2015 | 3/18/2015 | 3/18/2015 9:22:00 AM | A | DONE |
|
|
Doug and I went over fire dept signage
|
BLD14-01652
| FIRE-Final Inspection | 3/17/2015 | 3/18/2015 | 3/18/2015 7:10:25 AM | A | PASS |
|
|
life safety passed
|