BLD16-00162
| BLD-Wall cover | 3/18/2016 | 3/18/2016 | 3/20/2016 9:21:15 AM | P | PASS |
|
|
Shear // Austin Phone #: ###-####
|
BLD16-00506
| BLD-Conference | 3/18/2016 | 3/18/2016 | 3/20/2016 9:20:43 AM | P | DONE |
|
|
Jose Phone #: ###-#### After installing drain rock into old septic tank.....OK to pour footing.
|
BLD16-00505
| BLD-Footing | 3/18/2016 | 3/18/2016 | 3/20/2016 9:19:08 AM | P | PASS |
|
|
Jose Phone #: ###-####
|
BLD15-04006
| BLD-Energy code compliance | 3/17/2016 | 3/18/2016 | 3/20/2016 9:18:46 AM | P | PASS |
|
|
Insulation // Clarence Phone #: ###-####
|
BLD16-00761
| BLD-Foundation | 3/17/2016 | 3/18/2016 | 3/20/2016 9:18:03 AM | P | PASS |
|
|
Bob Phone #: ###-####
|
BLD16-00162
| BLD-Wall cover | 3/17/2016 | 3/18/2016 | 3/18/2016 12:15:21 PM | A | PASS |
|
|
Shear // Austin Phone #: ###-####
|
BLD15-02037
| BLD-Ceiling Grid Inspection | 3/17/2016 | 3/18/2016 | 3/18/2016 12:14:43 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Matt Ferguson
|
BLD15-02037
| BLD-Energy code compliance | 3/17/2016 | 3/18/2016 | 3/18/2016 12:14:06 PM | A | PASS |
|
|
The warehouse portion of the building needs ceiling insulation inspection. I left a letter from the architect for documentation in regards for doing blown-in in lieu of foam and batt at the roof sheathing. Phone #: ###-#### Inspection requested via web by Matt Ferguson
|
BLD15-03930
| BLD-Final | 3/17/2016 | 3/18/2016 | 3/18/2016 12:13:16 PM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter Need Fire final.
|
BLD15-01869
| BLD-Energy code compliance | 3/17/2016 | 3/18/2016 | 3/18/2016 9:54:10 AM | A | PASS |
|
|
Insulation // Clinton Phone #: ###-####
|
BLD15-01869
| BLD-Framing/Rough-in | 3/17/2016 | 3/18/2016 | 3/18/2016 9:53:28 AM | A | PASS |
|
|
Clinton Phone #: ###-####
|
BLD16-00208
| BLD-Final | 3/17/2016 | 3/18/2016 | 3/18/2016 7:58:28 AM | A | NR |
|
|
Justin Phone #: ###-#### Need Plumb final
|