Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD00-02379 BLD-Conference3/19/20013/19/20013/19/2001 12:00:00 AMAPART
Added by Inspector: 340 On 3/19/2001 9:15:45 AM w/ owner re c/n...ramp
BLD00-03426 BLD-Conference3/19/20013/19/20013/19/2001 12:00:00 AMAPASS
Added by Inspector: 340 On 3/19/2001 10:08:32 AM w/ Gary Mahachuk, proj mgr. (?) re Community hse...no inspections requested
BLD00-02752 BLD-Framing/Rough-in3/19/20013/19/20013/19/2001 12:00:00 AMAPART
Added by Inspector: 340 On 3/19/2001 10:00:29 AM west portion roof heathing ok; need termite report info
BLD00-00824 BLD-Final3/16/20013/19/20013/19/2001 12:00:00 AMANR
Larry Cantrell ###-####...need fire 3/19/2001 3:13:20 PM
BLD00-02752 BLD-Final3/19/20013/19/20013/19/2001 12:00:00 AMPNR
###-####\\nailing
BLD00-00081 BLD-Framing/Rough-in3/19/20013/19/20013/19/2001 12:00:00 AMPPART
Added by Inspector: 340 On 3/19/2001 4:11:39 PM reviewed insp reports for shot-crete; steel added at stairs ok.
BLD00-03519 BLD-Conference3/19/20013/19/20013/19/2001 12:00:00 AMPPART
Added by Inspector: 340 On 3/19/2001 4:41:29 PM rec'd eng'g resub...called arch John Price; need insps for concrete. called bldr, has had mti onsite, need to request city insps
BLD01-00032 BLD-Footing3/19/20013/19/20013/19/2001 12:00:00 AMPPART
###-####
BLD01-00425 BLD-Final3/19/20013/19/20013/19/2001 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 03/19/2001 at 08:54:41. Contact: ###-####...need glazing & bracing at wall top 3/20/2001 9:34:13 AM
BLD01-00582 BLD-Footing3/19/20013/19/20013/19/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 03/19/2001 at 09:01:04. Contact: .
BLD00-01531 BLD-Foundation3/19/20013/19/20013/19/2001 12:00:00 AMPPART
stem wall insp - mike ###-#### , ok pending report 3/19/2001 3:28:35 PM