Inspections for the day of: Monday, March 19, 2007.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Kinnear
TitleELE-INSPECTOR
Phone #794-1379
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE06-02581 Electrical Rough-In3/19/20073/19/20073/19/2007 3:05:12 PMPPASS
hank ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok cover ri
ELE07-00892 Temporary Service3/19/20073/19/20073/19/2007 3:04:47 PMPPASS
darrin; Phone #: ###-#### Internet Inspection Request from: Victoria Beall t/s u/g n ok
ELE07-00898 Electrical Rough-In3/19/20073/19/20073/19/2007 2:27:55 PMPPASS
Lynn; Phone #: ###-#### Internet Inspection Request from: Stacie Backus ok cover ri p/s u/g n ok
ELE06-04170 Rough-In Permanent Service3/19/20073/19/20073/19/2007 1:48:05 PMPPASS
lloyd ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith p/s u/g n ok no ri needed
ELE07-00549 Electrical Rough-In3/19/20073/19/20073/19/2007 1:03:45 PMPPASS
Need to look at the UFER Chris; Phone #: ###-#### Internet Inspection Request from: Stacie Backus ok cover ri for building ufer ground has to be to building rebar
ELE07-00870 Temporary Service3/15/20073/19/20073/19/2007 10:57:29 AMAPASS
Alan; Phone #: ###-#### Internet Inspection Request from: Stacie Backus t/s u/g n ok
ELE07-00871 Temporary Service3/15/20073/19/20073/19/2007 10:56:45 AMAPASS
Alan; Phone #: ###-#### Internet Inspection Request from: Stacie Backus t/s u/g n ok
ELE07-00818 Electrical Rough-In3/19/20073/19/20073/19/2007 10:26:56 AMAPASS
look on east wall for panel board install and inspect. thank you. contact:Joe
Phone #: ###-#### pk cover east wall for panel board
ELE06-03040 Final3/16/20073/19/20073/19/2007 10:10:15 AMAPASS
supervisor 02, rkpeterson final out on fab tool in bldg 24 in fab. this is one of several for Monday morning. thanks Ron Phone #: ###-#### ok final
ELE06-03038 Final3/16/20073/19/20073/19/2007 10:09:44 AMAPASS
supervisor 02 rkpeterson, Mike this is one fab tool of several to final out in bldg 24. I''ll be free after 9, monday morning. thanks Ron Phone #: ###-#### ok final
ELE06-02379 Final3/16/20073/19/20073/19/2007 10:09:11 AMAPASS
supervisor 02, rkpeterson Mike there are several FAb tools to final I''ll be busy from 8 to 9, but available this is in bldg 24 fab 4. Phone #: ###-#### ok final
ELE06-03630 Final3/16/20073/19/20073/19/2007 10:08:36 AMAPASS
Final inspection of clean rm. tool in building 16 for SUP03 ###-####. Phone #: ###-#### ok final
ELE06-02375 Final3/16/20073/19/20073/19/2007 10:08:02 AMAPASS
supervisor, 02 final, fab 4 bldg 24 tool needs to final out. Thanks Phone #: ###-#### ok final
ELE06-04535 Final3/15/20073/19/20073/19/2007 10:07:27 AMAPASS
supervisor 02, rkpeterson a bldg 24 fab 4 fab tool to final off, I''m here MOnday but busy from 8 to 9, call me ###-####. thanks Phone #: ###-#### ok final
ELE06-03951 Final3/15/20073/19/20073/19/2007 10:06:44 AMAPASS
supp 02 rkpeterson supervisor, ###-#### this is a fab tool in bldg 24 to final off.
I''ll be available after 9:00 if that works. Phone #: ###-#### ok final
ELE06-04063 Final3/16/20073/19/20073/19/2007 9:38:58 AMAPASS
SUP06, John Davis, I need a final for the conferance room in building 36 (area 7), 2nd floor. This will not final the electrical permit. Phone #: ###-#### ok final
ELE06-04491 Final3/16/20073/19/20073/19/2007 9:37:54 AMAPASS
SUP06, John Davis, I need a final for a few devices that are installed in a new wall installed in building 33. Phone #: ###-#### ok final