Inspections for the day of: Thursday, March 19, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE09-00318 Final3/19/20093/19/20093/19/2009 4:01:17 PMPPASS
completed as per conference Phone #: ###-#### Internet Inspection Request from: dennis mcneely ok to final, no card to sign, no esc this project
ESC08-01038 General Inspection3/19/20093/19/20093/19/2009 3:40:36 PMPPASS
looked ok
ELE08-02694 Final3/19/20093/19/20093/19/2009 3:38:48 PMPPASS
ok to final, no esc this project
ESC06-01299 General Inspection3/19/20093/19/20093/19/2009 3:11:37 PMPPASS
looked ok
ELE09-00182 Electrical Rough-In3/19/20093/19/20093/19/2009 2:55:54 PMPPASS
Alan Phone #: ###-#### ok to cover u/g for both garages
ELE09-00419 Final3/19/20093/19/20093/19/2009 1:31:43 PMPPASS
Shawn- call 30 mins prior to going for access Phone #: ###-#### called contractor, ok to final, signed occupancy card, no esc this project
ELE09-00443 Final3/18/20093/19/20093/19/2009 10:22:10 AMAPASS
need inspection on exisitng power pole that has been off over a year, also added a rv plug below panel. any questions call Andy @ ###-#### Phone #: ###-#### Internet Inspection Request from: Andy Rose called contractor, p/s, u/g ,exist, rec, ok, no esc this project
ELE07-03307 Electrical Rough-In3/18/20093/19/20093/19/2009 9:50:20 AMAPART
Contact: Neil Ramsey - Ceiling inspection in the Fire Command Room and Partial final for the shell & core please. Phone #: ###-#### Internet Inspection Request from: Deb Gooden ok to cover ceiling fire riser room, part final floors 10 thru roof ok anop