ESC10-00013
| General Inspection | 3/19/2010 | 3/19/2010 | 3/19/2010 1:57:02 PM | P | PART |
|
|
Construction entrances being installed, (Parkcenter and Penn.) Sediment barriers installed along Penn and partial on Parkcenter. Informed RP (Tom) that washout pit will be needed prior to placement of concrete.
|
ESC10-00165
| Site Preparation | 3/19/2010 | 3/19/2010 | 3/19/2010 7:12:26 AM | | CANC |
|
|
Inspection completed by inspector 316 on 3/18/10
|
ESC08-00927
| Site Preparation | 3/19/2010 | 3/19/2010 | 3/19/2010 7:12:01 AM | | CANC |
|
|
Inspection completed by Inspector 425 on 3/17
|