PLM12-00516
| Plumbing Rough-in | 3/19/2012 | 3/19/2012 | 3/19/2012 4:55:25 PM | P | PART |
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Kelley water test ok in all unit,s D W V test ok in four unit,s need to correct leak,s in two unit,s contractor to recall when ready
|
ESC12-00234
| Site Preparation | 3/19/2012 | 3/19/2012 | 3/19/2012 4:06:12 PM | | PASS |
|
|
no construction activities at this time
|
PLM11-01881
| Plumbing Rough-in | 3/19/2012 | 3/19/2012 | 3/19/2012 4:04:32 PM | P | PART |
|
|
tom Phone #: ###-#### rough-in marked on plans test ok
|
PLM11-02096
| Final | 3/19/2012 | 3/19/2012 | 3/19/2012 1:31:45 PM | P | PASS |
|
|
Randy is the contact Phone #: ###-#### >> Inspection requested via web by Randy Powell
|
ESC11-00844
| General Inspection | 3/19/2012 | 3/19/2012 | 3/19/2012 10:13:34 AM | | PASS |
|
|
site locked up no activities at this time
|
PLM12-00292
| Final | 3/16/2012 | 3/19/2012 | 3/19/2012 10:12:14 AM | A | FAIL |
|
|
JOB CONTACT IS JIMMY Phone #: ###-#### >> Inspection requested via web by ADAM WARR need to remove water flex connector from T&P valve and replace with approved material need to provide expansion tank on water heater need to adjust permit for new restroom addition called contractor will recall when ready
|