FIR11-00651
| INSP-Supply line flush | 3/19/2012 | 3/19/2012 | 3/19/2012 5:44:04 PM | P | PART |
|
|
UG fire supply line flush completed acceptable.
|
FIR12-00103
| INSP-Conference | 3/19/2012 | 3/19/2012 | 3/19/2012 5:43:24 PM | A | DONE |
|
|
Regarding site inspection schedule.
|
BLD11-01743
| FIRE-Sprinkler Rough-in | 3/19/2012 | 3/19/2012 | 3/19/2012 5:42:26 PM | A | PART |
|
|
Dry system rough-in inspection completed. Discussed protection for combustible concealed spaces and allowable exceptions per NFPA 13.
|
FIR11-00575
| INSP-Alarm Testing | 3/19/2012 | 3/19/2012 | 3/19/2012 5:39:54 PM | A | PART |
|
|
Completed fire sprinkler monitoring test for systems installed to date- system 4,10,2, 8 duct and 8OH flows and tampers. Items noted include; incorrect descriptor at duct system 8 control valve, missing PIV tamper, one incomplete riser manifold, deluge valve for opening protection is unfinished.
|
FIR11-00664
| INSP-Final Inspection | 3/19/2012 | 3/19/2012 | 3/19/2012 5:22:49 PM | A | PART |
|
|
Tamper switch at the fire sprinkler supply control valve tested satisfactory. Final pending FIR11-00575.
|