Inspections for the day of: Wednesday, March 19, 2014.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-01263 Random Inspection3/19/20143/19/20143/19/2014 3:24:32 PMPPASS
Perimeter wattles retaining sediment on site. SWPPP posted at construction entrance. No corrections at this time.
ESC13-00758 Aging Inspection3/19/20143/19/20143/19/2014 3:16:13 PM PART
Pine Tree Village has been recently swept due to corrections issued on the project. DI's have protection and no track out on interior streets or out to Maple Grove.

Need to have SWPPP and ESC permits clearly posted.
ESC13-00705 Aging Inspection3/19/20143/19/20143/19/2014 2:37:21 PM PASS
Finaled.
ESC13-00705 DOC - Permit Finaled3/19/20143/19/20143/19/2014 2:36:56 PMPPASS
Yard graded below sidewalk and alley. Construction materials removed from site. Landscaping on going by homeowner. ESC conditions satisfied.
ESC13-00828 Aging Inspection3/19/20143/19/20143/19/2014 2:15:30 PM PASS
Finaled.
ESC14-00042 General Inspection3/19/20143/19/20143/19/2014 2:14:29 PM PASS
Backstops have been installed. Some minor work remaining. Pavement behind backstop will be swept at end of day and when infield is regraded.
ESC13-00828 DOC - Permit Finaled3/19/20143/19/20143/19/2014 1:54:04 PMPPASS
Addition to back of house is complete. BLD permits are finaled; ESC conditions satisfied.
ESC14-00043 General Inspection3/19/20143/19/20143/19/2014 11:58:06 AM PASS
Foundation has been poured. Permit posted. No trackout or sediment runoff. Somerset Ridge #5 was recently hydroseeded in surrounding areas.
ESC13-00930 General Inspection3/19/20143/19/20143/19/2014 11:19:38 AM PASS
No track out. Work contained within existing yard and landscaping which acts as a buffer. Approved.
ESC13-00938 General Inspection3/19/20143/19/20143/19/2014 11:07:44 AM PASS
BLD permit has been finaled, but yard is not yet stabilized or landscaped. ESC permit conditions are not yet satisfied, but there no corrections required at this time.
ESC13-00849 General Inspection3/19/20143/19/20143/19/2014 11:02:28 AM PASS
Finaled.
ESC13-00849 DOC - Permit Finaled3/19/20143/19/20143/19/2014 11:02:13 AMPPASS
Modular building has been installled. Stormwater drainage is complete, all construction materials removed and sediment swept up. ESC conditions satisfied.
ESC14-00144 Site Preparation3/18/20143/19/20143/19/2014 10:52:20 AMAPASS
jim Phone #: ###-####

SWPPP and ESC permit posted onsite. Perimeter wattles have been set in place, but rock construction entrance is not yet installed. No surface waters or creeks running through site, which is also relatively flat.

Will need to watch dust once the vegetation is disturbed. When stockpile hauling begins, a heavy duty construction entrance will be necessary.
ESC14-00022 Random Inspection3/19/20143/19/20143/19/2014 10:50:01 AMPPASS
Initial phase of East Valley Subdivision inspected during site prep for new phase that is scheduled to begin. Diversion channel behind grading on hillside is in good condition. No trackout observed, but they will need to install a heavy duty construction entrance when they haul the existing stockpiles away.
ESC13-00967 Random Inspection3/19/20143/19/20143/19/2014 9:42:40 AMACANC
Grading has been completed, but parking lot and stormwater structures are in progress. No track out to Century or Cole, DIs in area are protected.
ESC13-01182 General Inspection3/19/20143/19/20143/19/2014 9:38:51 AM PASS
No ESC violations or fugitive dust observed. WIP. Approved.
ESC13-00843 DOC - Permit Finaled3/19/20143/19/20143/19/2014 9:26:23 AMPPASS
Project complete and landscaped. Edge is open for business. No outstanding ESC issues.
ESC13-00843 General Inspection3/19/20143/19/20143/19/2014 9:08:55 AM PASS
ESC13-01185 General Inspection3/19/20143/19/20143/19/2014 8:39:46 AM PASS