BLD00-00170
| BLD-Footing | 3/1/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | A | NR |
|
|
After 10:00; Larry; ###-####
|
BLD00-00483
| BLD-Footing | 3/1/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 09:48:14. Contact: ###-####.
|
BLD99-02751
| BLD-Framing/Rough-in | 3/1/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | A | FAIL |
|
|
nailing pattern on the sheet rock Bob ###-#### No plans onsite. Talked with sheetrocker about setting them out. 3/2/00 2:25:45 PM
|
BLD99-02585
| BLD-Energy code compliance | 3/1/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 18:24:57. Contact: ###-####. Still need to complete upper floor vapor burrier. 3/2/00 2:26:06 PM
|
BLD99-03581
| BLD-Wall cover | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/02/2000 at 08:11:11. Contact: ###-####. OK to side exterior. 3/3/00 9:05:12 AM
|
BLD99-03581
| BLD-Other | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | PASS |
|
|
|
BLD99-01784
| BLD-Foundation | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | PASS |
|
|
mana ###-#### found wall insp
|
BLD99-03497
| BLD-Energy code compliance | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | PASS |
|
|
Jack ###-####
|
BLD00-00170
| BLD-Footing | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | CANC |
|
|
dave ###-#### Done by 340 3/3/00 9:05:02 AM
|
BLD99-02585
| BLD-Energy code compliance | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 03/02/2000 at 11:15:42. Contact: . Still not done upper floor vapor C/N. posted 2nd trip today. 3/3/00 9:05:44 AM
|
BLD99-03737
| BLD-Footing | 3/2/2000 | 3/2/2000 | 3/2/2000 12:00:00 AM | P | PART |
|
|
Footing ok subject to engineers compaction report of MIN 951.
|