Inspections for the day of: Thursday, March 2, 2006.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00659 INSP-Sprinkler Rough-in/Hydro3/2/20063/2/20063/3/2006 1:27:50 PMPDEFR
Inspection to be scheduled for 3/3 as discussed with contractor.
BLD01-01632 FIRE-Final Inspection3/1/20063/2/20063/3/2006 1:26:56 PMACANC
No time to perform this inspection today, to be rescheduled.
FIR06-00122 INSP-Final Inspection3/2/20063/2/20063/3/2006 12:53:54 PMPCANC
No time for this inspection today, to be rescheduled per conversation with contractor for 3/3.
FIR06-00035 INSP-Final Inspection3/1/20063/2/20063/2/2006 5:50:39 PMPFAIL
The sample tubes in one duct are incorrectly oriented, one AHU is non-functional and thus cannot be tested at this time, av's and EOL tested okay.
BLD05-03100 FIRE-Final Inspection3/2/20063/2/20063/2/2006 3:57:57 PMPPASS
Fire life safety passed inspection.
FIR05-00615 INSP-Final Inspection2/27/20063/2/20063/2/2006 3:14:27 PMAPASS
Fire alarm is acceptable for final.
FIR05-00611 INSP-Final Inspection2/28/20063/2/20063/2/2006 3:13:21 PMAFAIL
Fire sprinkler must meet requirements of NFPA 13 2002 7.3.2.4 (3) with respect to the installation of pendent sprinklers on preaction systems.
FIR05-00610 INSP-Alarm Testing2/28/20063/2/20063/2/2006 3:07:36 PMAFAIL
Visual notification devices within the remodeled area are not in sync as required, vesda tested okay, door release is functional, one heat detector remains to be tested.
BLD05-02620 FIRE-Final Inspection2/27/20063/2/20063/2/2006 3:02:24 PMANR
The project related alarm and sprinkler permits must pass inspection prior to life safety final approval.
MIS06-00041 FIR-Final2/27/20063/2/20063/2/2006 3:00:18 PMAFAIL
Remove manual thumbturns at the main entry/exit door and the door from warehouse area, keyed locking hardware is allowed at the main entry/exit with signage above the door, cover open electrical boxes and secure loose/unused wire, provide fire extinguishers as discussed for the office and warehouse areas, provide building address.
FIR05-00456 INSP-Final Inspection2/27/20063/2/20063/2/2006 1:20:10 PMAPASS
Fire alarm passed inspection.
FIR05-00807 INSP-Final Inspection3/1/20063/2/20063/2/2006 1:17:14 PMAPASS
Requested corrections have been made, fire alarm tested satisfactory.
FIR06-00126 INSP-Sprinkler Rough-in3/1/20063/2/20063/2/2006 9:36:47 AMAPART
Inspected thrust block at 90, ductile stub-in, tracer wire, and NRS valve for PI, good for cover at these areas, street connection is not complete at this time, need retaining method at riser flange.