BLD05-01409
| FIRE-Final Inspection | 2/28/2006 | 3/2/2006 | 3/2/2006 4:30:42 PM | P | FAIL |
|
|
See correction notice for items
|
FIR05-00425
| INSP-Sprinkler Rough-in/Hydro | 3/1/2006 | 3/2/2006 | 3/2/2006 3:08:17 PM | A | PASS |
|
|
200 LB hydro Test on 1st Flr dry System passed.
|
FIR05-00651
| INSP-Final Inspection | 3/2/2006 | 3/2/2006 | 3/2/2006 3:07:35 PM | P | PASS |
|
|
Permit finaled
|
FIR05-00779
| INSP-Final Inspection | 3/2/2006 | 3/2/2006 | 3/2/2006 3:07:00 PM | P | PASS |
|
|
permit finaled
|
FIR06-00076
| INSP-Sprinkler Rough-in | 3/1/2006 | 3/2/2006 | 3/2/2006 11:24:31 AM | A | PASS |
|
|
Sprinkler piping is ok to cover
|
FIR05-00814
| INSP-Sprinkler Rough-in | 3/1/2006 | 3/2/2006 | 3/2/2006 11:24:06 AM | A | PASS |
|
|
Sprinkler piping is ok to cover
|
BLD04-02937
| FIRE-Conference | 3/1/2006 | 3/2/2006 | 3/2/2006 10:12:57 AM | A | DONE |
|
|
I had a conference with the superintendant and Treasure Valley Fire. Heads will not be required under the beam since it is only 10.5" wide but the sidewall head sprinkler deflectors exceed 6" from the beam/wall and will need to be relocated along both sides of the beams.
|
BLD05-01935
| FIRE-Final Inspection | 3/1/2006 | 3/2/2006 | 3/2/2006 10:10:44 AM | A | PASS |
|
|
Life safety finaled
|
BLD05-02937
| FIRE-Final Inspection | 3/1/2006 | 3/2/2006 | 3/2/2006 9:20:42 AM | A | PASS |
|
|
Life safety finaled
|