FIR08-00766
| INSP-Sprinkler Rough-in/Hydro | 3/2/2009 | 3/2/2009 | 3/3/2009 9:49:07 AM | P | PART |
|
|
Verified thrust blocking at 45's adjacent to the storm drain at the Freight street entrance.
|
FIR08-00863
| INSP-Sprinkler Rough-in/Hydro | 3/2/2009 | 3/2/2009 | 3/2/2009 4:55:30 PM | P | PART |
|
|
Overhead rough-in completed okay with the exception of two mixed response heads at the concealed canopy area to be replaced, missing expansion tank for the antifreeze system, some items at the riser are not yet finished.
|
BLD08-02394
| FIRE-Final Inspection | 3/2/2009 | 3/2/2009 | 3/2/2009 4:51:18 PM | P | PASS |
|
|
Field verified correction item has been completed, fire life safety finaled.
|
FIR09-00106
| INSP-Conference | 3/2/2009 | 3/2/2009 | 3/2/2009 4:48:41 PM | P | DONE |
|
|
On site conference regarding additional building modifications at the tenant remodel area which will affect fire sprinkler coverage.
|
FIR08-00863
| INSP-Sprinkler Rough-in/Hydro | 2/27/2009 | 3/2/2009 | 3/2/2009 4:47:13 PM | A | PART |
|
|
Both the underground supply pipe and overhead wet and antifreeze systems passed hydrostatic testing.
|
FIR08-00776
| INSP-Alarm Testing | 2/26/2009 | 3/2/2009 | 3/2/2009 4:44:11 PM | A | PART |
|
|
See locations initialed on approved plan set with today's date for three in duct detectors, two area detectors and two notification devices tested, noted one HVAC grill to be relocated as discussed.
|