Inspections for the day of: Monday, March 2, 2009.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00766 INSP-Sprinkler Rough-in/Hydro3/2/20093/2/20093/3/2009 9:49:07 AMPPART
Verified thrust blocking at 45's adjacent to the storm drain at the Freight street entrance.
FIR08-00863 INSP-Sprinkler Rough-in/Hydro3/2/20093/2/20093/2/2009 4:55:30 PMPPART
Overhead rough-in completed okay with the exception of two mixed response heads at the concealed canopy area to be replaced, missing expansion tank for the antifreeze system, some items at the riser are not yet finished.
BLD08-02394 FIRE-Final Inspection3/2/20093/2/20093/2/2009 4:51:18 PMPPASS
Field verified correction item has been completed, fire life safety finaled.
FIR09-00106 INSP-Conference3/2/20093/2/20093/2/2009 4:48:41 PMPDONE
On site conference regarding additional building modifications at the tenant remodel area which will affect fire sprinkler coverage.
FIR08-00863 INSP-Sprinkler Rough-in/Hydro2/27/20093/2/20093/2/2009 4:47:13 PMAPART
Both the underground supply pipe and overhead wet and antifreeze systems passed hydrostatic testing.
FIR08-00776 INSP-Alarm Testing2/26/20093/2/20093/2/2009 4:44:11 PMAPART
See locations initialed on approved plan set with today's date for three in duct detectors, two area detectors and two notification devices tested, noted one HVAC grill to be relocated as discussed.