Inspections for the day of: Monday, March 2, 2009.
Number of inspections: 42
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-02182 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 4:26:27 PMPPASS
jim Phone #: ###-####. 1st. floor, 2nd layer of 5/8 type x rock, both sides for 2hr. fire wall.
BLD08-02183 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 4:25:45 PMPPASS
jim Phone #: ###-####. 1st. floor, 2nd. layer of 5/8 type x rock, both sides for 2hr. fire wall.
BLD08-02184 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 4:25:00 PMPPASS
jim Phone #: ###-####. 1st. floor, 2nd. layer of 5/8 type x rock both sides for 2hr. fire wall.
BLD08-02185 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 4:24:09 PMPPASS
jim Phone #: ###-####. 1st. floor, 2nd. layer of 5/8 type x rock, both sides for 2hr. fire wall.
ESC08-00871 BMP Violation3/2/20093/2/20093/2/2009 3:42:30 PMPPASS
ESC08-00872 BMP Violation3/2/20093/2/20093/2/2009 3:42:15 PMPPASS
ESC08-00873 BMP Violation3/2/20093/2/20093/2/2009 3:42:02 PMPPASS
ESC08-00874 BMP Violation3/2/20093/2/20093/2/2009 3:41:51 PMPPASS
ESC08-00880 Random Inspection3/2/20093/2/20093/2/2009 3:41:25 PMPPASS
ESC08-00881 Random Inspection3/2/20093/2/20093/2/2009 3:41:10 PMPPASS
ESC08-00882 Random Inspection3/2/20093/2/20093/2/2009 3:40:55 PMPPASS
ESC08-00883 Random Inspection3/2/20093/2/20093/2/2009 3:40:40 PMPPASS
BLD08-02190 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:59:04 PMPCANC
jim Phone #: ###-####
BLD08-02192 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:58:41 PMPCANC
jim Phone #: ###-####
BLD08-02191 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:58:26 PMPCANC
jim Phone #: ###-####
BLD08-02193 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:58:12 PMPCANC
jim Phone #: ###-####
ESC08-00888 Random Inspection3/2/20093/2/20093/2/2009 2:53:55 PMPPASS
BLD08-02196 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:53:32 PMPPART
jim Phone #: ###-####. 2nd. floor, 1st. layer, both sides type x rock for 2hr. fire wall.
ESC08-00886 Random Inspection3/2/20093/2/20093/2/2009 2:50:49 PMPPASS
BLD08-02195 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:50:33 PMPPASS
jim Phone #: ###-####. 2nd. floor, 2nd. later, remaining side of 5/8 type x rock for 2hr. fire wall.
ESC08-00885 Random Inspection3/2/20093/2/20093/2/2009 2:49:27 PMPPASS
BLD08-02194 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:49:10 PMPPASS
jim Phone #: ###-####. 2nd. floor, 2nd layer, remaining side of 5/8 type x rock. ok.
BLD08-02186 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:45:16 PMPPASS
jim Phone #: ###-####. Both layers of 5/8 type x rock at overbuild area for 2hr. fire wall.
ESC08-00875 BMP Violation3/2/20093/2/20093/2/2009 2:41:40 PMPPASS
BLD08-02187 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:40:57 PMPPASS
jim Phone #: ###-####. both layers of 5/8 type x rock at overbuild areas. ok.
ESC08-00877 BMP Violation3/2/20093/2/20093/2/2009 2:39:38 PMPPASS
BLD08-02188 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:39:20 PMPPART
jim Phone #: ###-####. 2nd. floor, 1st. layer, one side only, type x 5/8 rock for 2hr. fire wall.
ESC08-00878 BMP Violation3/2/20093/2/20093/2/2009 2:37:46 PMPPASS
ESC08-00879 BMP Violation3/2/20093/2/20093/2/2009 2:37:26 PMPPASS
BLD08-02189 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 2:37:04 PMPPART
jim Phone #: ###-####. 2nd floor, 1st. layer 5/8 typex, one side only for 2hr. fire wall.
BLD08-02395 BLD-Footing3/2/20093/2/20093/2/2009 2:26:53 PMPPASS
Ian Phone #: ###-####. Exterior column pad footings.
ESC08-00981 Site Preparation3/2/20093/2/20093/2/2009 1:44:17 PMPPASS
ESC permit signs have been posted at controlled enterance. Generak site conditions were good.
ESC08-00895 Random Inspection3/2/20093/2/20093/2/2009 10:27:40 AMAPASS
BLD08-02201 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 10:27:20 AMAPASS
Attachment of 5/8 typex rock for 2hr. fire walls at overbuild areas. ok.
ESC08-00896 Random Inspection3/2/20093/2/20093/2/2009 10:26:23 AMAPASS
BLD08-02202 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 10:25:59 AMAPASS
Attachment of 5/8 typex rock for 2hr. firewalls at overbuild areas.
ESC08-00897 Random Inspection3/2/20093/2/20093/2/2009 10:25:07 AMAPASS
BLD08-02203 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 10:24:44 AMAPASS
Attacment of 5/8 typex rock for 2hr. walls at over build areas. ok.
ESC08-00898 Random Inspection3/2/20093/2/20093/2/2009 10:23:52 AMAPASS
BLD08-02204 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 10:23:05 AMAPASS
Nailing for 5/8 typex rock on 2hr. walls at over build areas.ok.
BLD08-02195 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 10:13:32 AMAPASS
jim Phone #: ###-####. 2nd. floor, 1st. layer, remaining side of 5/8 type x rock for 2hr. fire wall.
BLD08-02194 BLD-Framing/Rough-in3/2/20093/2/20093/2/2009 10:12:26 AMAPASS
jim Phone #: ###-####. 2nd. floor, 1st. layer remaining side of 5/8 type x rock for 2hr. wall.