FIR10-00007
| INSP-Final Inspection | 3/2/2010 | 3/2/2010 | 3/2/2010 4:51:00 PM | P | PASS |
|
|
On site fire alarm work tested acceptable, contractor to provide list of signals sent at todays inspection per discussion.
|
BLD10-00305
| FIRE-Final Inspection | 3/2/2010 | 3/2/2010 | 3/2/2010 4:48:53 PM | P | PASS |
|
|
Corrections completed and pending are acceptable for fire life safety final. NOTE: See MIS permit for notice of violation regarding necessary fire alarm work.
|
FIR09-00536
| INSP-Sprinkler Rough-in | 3/2/2010 | 3/2/2010 | 3/2/2010 4:47:08 PM | P | PART |
|
|
Overhead hydrostatic test for the new dry system at the attic passed inspection.
|
BLD10-00339
| FIRE-Final Inspection | 3/1/2010 | 3/2/2010 | 3/2/2010 4:45:32 PM | P | PASS |
|
|
Correction notice items field verified for completion, life safety finaled.
|
FIR10-00054
| INSP-Sprinkler Rough-in | 3/2/2010 | 3/2/2010 | 3/2/2010 4:44:31 PM | P | PART |
|
|
Underground fire supply line and stub-in including the ductile riser, two thrust blocks and two lengths of C-900 outside the new building as marked on approved plans are okay for bury.
|