Inspections for the day of: Tuesday, March 2, 2010.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00286 General Inspection3/1/20103/2/20103/2/2010 3:25:59 PMPPART
Minimal controls in place but no discharge is apparent. Additional rock on entrances should be installed, informed RP.
ESC09-00352 General Inspection2/26/20103/2/20103/2/2010 3:06:32 PMPPART
Met with RP, Gary Howard and Clint Smith. Discussions regarding upcoming pedestrian bridge across Walling's Creek. Recommended silt curtain downstream of project. Also, at NW side of project additional sediment barriers are needed since the elevation of site has been raised. Discussion regarding stabilization, Ok by us to have a green zone around the perimeter of the park and then a top layer of angular rock on top of the pit run as well as for the main park road until asphalt is layed.