FIR11-00067
| INSP-Conference | 3/2/2011 | 3/2/2011 | 3/2/2011 3:51:45 PM | P | DONE |
|
|
I went over duct detector placement with Greg.
|
FIR10-00514
| INSP-Sprinkler Rough-in | 3/1/2011 | 3/2/2011 | 3/2/2011 3:09:03 PM | P | PASS |
|
|
Todays inspection was just for the rough-in on the second floor mains, branchlines and arm overs. Additional inspections will be required once the ceiling grid has been installed to verify final pendant sprinkler spacing.
|
FIR10-00655
| INSP-Final Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 3:03:51 PM | P | FAIL |
|
|
Replace the painted sprinkler pendants. Replace the painted eschuteons. Replace the missing eschuteons.
|
FIR10-00610
| INSP-Final Inspection | 3/1/2011 | 3/2/2011 | 3/2/2011 2:57:25 PM | A | PASS |
|
|
Permit finaled
|
FIR10-00107
| INSP-Final Inspection | 2/23/2011 | 3/2/2011 | 3/2/2011 12:23:53 PM | A | PASS |
|
|
permit finaled
|
FIR10-00108
| INSP-Final Inspection | 2/23/2011 | 3/2/2011 | 3/2/2011 11:26:53 AM | A | PASS |
|
|
Permit finaled
|