ESC10-00854
| BMP Violation | 3/1/2011 | 3/2/2011 | 3/3/2011 2:27:30 PM | P | FAIL |
|
|
Verbal to RP: Final Notice: 1. Clean up all sediment and debris off of all hard surfaces. 2. Maintain and install additional sediment barriers along the perimeter. 3. Maintain storm drain inlet protection. Failure to comply will result in a STOP WORK ORDER.
|
ESC11-00055
| General Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 5:28:11 PM | | PART |
|
|
Waiting on the hydroseeding to occur on all disturbed soil.
|
ESC10-00553
| General Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 2:50:41 PM | | PEND |
|
|
Waiting on the RP to contact me to setup a time to access the project to inspect.
|
ESC10-00600
| General Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 2:15:42 PM | | PASS |
|
|
|
ESC10-00900
| Complaint Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 1:45:54 PM | P | PASS |
|
|
Stockpile proitected with a sediment barrier. The ruling has been made that not protection is needed on the stockpile.
|