Inspections for the day of: Wednesday, March 2, 2016.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00105 INSP-Sprinkler Rough-in3/1/20163/2/20163/2/2016 3:12:15 PMPPASS
Remaining underground piping is ok to cover. The initial portion of the piping was installed by United Water. Shilo has provided a letter assuming responcibility
FIR16-00055 INSP-Final Inspection2/26/20163/2/20163/2/2016 2:45:46 PMPFAIL
There were no city approved plans on site. I noted two devices in the Lobby area that do not match the plans provided. No test performed.
FIR16-00020 INSP-Final Inspection2/29/20163/2/20163/2/2016 1:50:04 PMPFAIL
Since the elevator contractor did not show up we could not get acces to the last heat detector to be tested in the elevator pit.
BLD15-02730 FIRE-Final Inspection3/1/20163/2/20163/2/2016 1:48:44 PMPFAIL
Need the project related fire alarm permit finaled, remove the exit sign directing people to the elevator, repair the non-functional exit signs/emergency lights, provide additional signage for the elevator on the second floor.
BLD15-04449 FIRE-Final Inspection3/1/20163/2/20163/2/2016 10:53:38 AMAFAIL
All items have been corrected except that a FIR permit is needed for the sprinkler head change out. When the FIR permit is finaled the life safety can be finaled.
BLD15-04039 FIRE-Final Inspection3/2/20163/2/20163/2/2016 9:32:12 AMPPASS
Life safety passed. Per owner, she contacted Carl in plan review and only the door hardware for the Activity Room needs to be ADA (has not been installed yet).
BLD16-00317 FIRE-Final Inspection3/1/20163/2/20163/2/2016 8:44:55 AMAPASS
Life safety passed
FIR16-00096 INSP-Sprinkler Rough-in3/1/20163/2/20163/2/2016 7:46:29 AMAPASS
Rough-in passed. Piping can be covered.