PLM00-00313
| Final | 3/17/2000 | 3/20/2000 | 3/20/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/17/2000 at 14:01:32. Contact: ###-####.
|
PLM00-00159
| Final | 3/17/2000 | 3/20/2000 | 3/20/2000 12:00:00 AM | A | PASS |
|
|
KEN 888-/6292 RE-INSP FN
|
PLM00-00023
| Groundwork | 3/17/2000 | 3/20/2000 | 3/20/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/17/2000 at 16:25:44. Contact: ###-####.
|
PLM00-00728
| Plumbing Rough-in | 3/20/2000 | 3/20/2000 | 3/20/2000 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM00-00715
| Water and/or Sewer | 3/20/2000 | 3/20/2000 | 3/20/2000 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM00-00654
| Plumbing Rough-in | 3/20/2000 | 3/20/2000 | 3/20/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/20/2000 at 11:03:54. Contact: ###-####.
|