PLM01-00764
| Sprinkler (Final) | 3/19/2001 | 3/20/2001 | 3/20/2001 12:00:00 AM | A | PASS |
|
|
BACKFLOW-- ROB-- ###-####
|
PLM01-00764
| Sprinkler (Final) | 3/19/2001 | 3/20/2001 | 3/20/2001 12:00:00 AM | A | PASS |
|
|
BACKFLOW-- ROB-- ###-####
|
PLM01-00740
| Groundwork | 3/20/2001 | 3/20/2001 | 3/20/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 03/20/2001 at 08:26:21. Contact: ###-####.this is a plumbing rough-in toilet and tub vent needs to be 6-inches above flood level rim of fixture before offsetting horizontally 3/20/2001 2:22:42 PM
|
PLM01-00740
| Plumbing Rough-in | 3/20/2001 | 3/20/2001 | 3/20/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 360 On 3/20/2001 3:08:59 PM
|