BLD98-03705
| BLD-Footing | 3/15/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 03/15/2002 at 15:57:40. Contact: . pend report from mti 3/20/2002 2:03:46 PM
|
BLD00-03624
| BLD-Wall cover | 3/19/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 03/19/2002 at 10:14:17. Contact: ###-####. c/n: complete air seal, nail-off panels, show truss calcs, etc 3/20/2002 4:58:16 PM
|
MIS02-00058
| BLD-Final | 3/19/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | P | DONE |
|
|
SANDRA ###-#### NEED TO CHECK STAIR WAY ON # 66 AND CALL SUPERINTENDENT ; called Sandra, I agree that extinguisher box is too close to handrail...req's release to pass box on stair. Recommended she consult atty. 3/20/2002 5:00:22 PM
|
BLD01-00234
| BLD-Final | 3/19/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 03/19/2002 at 17:17:08. Contact: ###-####.
|
BLD98-03705
| BLD-Footing | 3/20/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 09:34:06. Contact: . wip...MTI onsite. 3/20/2002 2:08:38 PM
|
BLD00-01649
| BLD-Final | 3/20/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | P | NR |
|
|
###-#### MEL awaiting Mti's approval of fireproofing test at int. column & beam. 3/20/2002 1:48:30 PM
|
BLD02-00561
| BLD-Footing | 3/20/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | P | NR |
|
|
###-####
|
BLD02-00167
| BLD-Conference | 3/20/2002 | 3/20/2002 | 3/20/2002 12:00:00 AM | P | FAIL |
|
|
###-#### LON would like to have conf at work site; obtain legible plans/eng'g and compile list of questions, then recall when ready 3/20/2002 3:25:32 PM
|