BLD17-03338
| BLD-Aging Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 4:37:41 PM | | PASS |
|
|
Foundation work completed. Will final when project is completed.
|
BLD17-00340
| BLD-Aging Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 4:36:55 PM | | PASS |
|
|
|
MIS17-00389
| MIS-Aging Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 4:35:23 PM | | DONE |
|
|
|
MIS17-00389
| DOC - Permit Finaled | 3/20/2018 | 3/20/2018 | 3/20/2018 4:35:16 PM | P | PASS |
|
|
plumbing permit issued and finaled.
|
MIS17-00197
| MIS-Aging Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 4:32:50 PM | | DEFR |
|
|
|
BLD17-03994
| BLD-Final | 3/19/2018 | 3/20/2018 | 3/20/2018 4:32:14 PM | P | NR |
|
|
late as poss // Tommy Lyles Phone #: ###-####. Fire/life/safety final failed. Needs electrical and fire sprinkler finals. Will also need demo permit finaled as well.
|
ESC17-00102
| General Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 4:07:34 PM | P | FAIL |
|
|
Needs to sweep all silts from hard surfaces. Appeares no maintenace has been taken place. Noted excessive trackout. All Either no BMP's in place, or the ones in place are in non functioning state.
|
BLD17-02429
| BLD-Framing/Rough-in | 3/19/2018 | 3/20/2018 | 3/20/2018 3:34:51 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Complete lateral bracing, reapir firewall, install missed header.
|
BLD17-03755
| BLD-Ceiling Grid Inspection | 3/19/2018 | 3/20/2018 | 3/20/2018 2:35:59 PM | P | PASS |
|
|
Please contact JP at ###-#### Phone #: ###-#### Inspection requested via web by Mattie Botero.
|
BLD17-03581
| BLD-Other | 3/20/2018 | 3/20/2018 | 3/20/2018 2:22:46 PM | P | DONE |
|
|
roof shear // Adam Joslin Phone #: ###-####
|
BLD16-04486
| BLD-Other | 3/20/2018 | 3/20/2018 | 3/20/2018 2:04:24 PM | P | PASS |
|
|
Fire rated assembly at roof eaves. Phone #: ###-#### Inspection requested via web by Sam Brown
|
BLD18-00116
| BLD-Framing/Rough-in | 3/19/2018 | 3/20/2018 | 3/20/2018 2:00:53 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Philip Yates. Complete lateral bracing on A02, A03 and A04 trusses. Nail 2ply BG01 box truss per the engineering. Roll block floor joist at cantilevers. Provide 2x6 blocking under either end of BGO1 truss to complte load path. Install the additional SDS screws on ledgers. ok to insulate. Correction notice posted.
|
BLD18-00432
| BLD-Framing/Rough-in | 3/20/2018 | 3/20/2018 | 3/20/2018 11:26:59 AM | A | PART |
|
|
Interior steel stud framed wall ok. Noted that an existing door/sidelight has been removed from the existing alcove and reinstalled in new interior wall. Side light is wired glass and no longer complies as tempered glazing. Glazing will need to removed and replaced with tempered glazing prior to final.
|
BLD17-03716
| BLD-Framing/Rough-in | 3/19/2018 | 3/20/2018 | 3/20/2018 9:34:31 AM | A | PASS |
|
|
call ahead 15 mins------Jim Phone #: ###-####
|
BLD18-00207
| BLD-Energy code compliance | 3/19/2018 | 3/20/2018 | 3/20/2018 8:46:03 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Philip Yates
|
BLD17-01641
| BLD-Footing | 3/19/2018 | 3/20/2018 | 3/20/2018 8:45:47 AM | A | PASS |
|
|
jose Phone #: ###-####
|
BLD18-00432
| BLD-Framing/Rough-in | 3/19/2018 | 3/20/2018 | 3/20/2018 12:00:00 AM | A | CANC |
|
|
Keith Lemons Phone #: ###-####
|