MEC19-01093
| Rough-in | 3/20/2019 | 3/20/2019 | 3/20/2019 3:10:07 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Aaron Toomey - No equipment installed at time of rough in
|
MEC19-01128
| Conference | 3/20/2019 | 3/20/2019 | 3/20/2019 2:16:49 PM | P | DONE |
|
|
Went on inspection with Jack
|
MEC19-00679
| Final | 3/19/2019 | 3/20/2019 | 3/20/2019 10:57:50 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Debbie Marino - This work was inspected, tested, and passed under permit MEC18-00396
|
MEC19-00679
| Pressure Test | 3/19/2019 | 3/20/2019 | 3/20/2019 10:56:24 AM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Debbie Marino
|
MEC19-00798
| Rough-in | 3/19/2019 | 3/20/2019 | 3/20/2019 10:05:43 AM | A | PASS |
|
|
grid inspection duct insulate Phone #: ###-#### Inspection requested via web by fred lopez - Okay to cover ceiling
|