BLD96-00162
| INSP - Framing/Rough-in | 3/20/1996 | 3/21/1996 | 12/1/1996 12:00:00 AM | P | PASS |
|
|
/ / 340 - READY THURS PM c/n ok
|
BLD96-00288
| INSP - Framing/Rough-in | 3/21/1996 | 3/21/1996 | 12/1/1996 12:00:00 AM | P | PASS |
|
|
03/21/96 340 - left note to insul plenums...seal boots
|
BLD96-00610
| INSP - Energy code compliance | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD96-00637
| INSP - Footings | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 - EXCAV. & FTG FOR ADD'N TO POLE BLDG
|
BLD96-00162
| INSP - Energy code compliance | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD96-00288
| INSP - Energy code compliance | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PART |
|
|
/ / 340 - need to ins boots, plenums
|
BLD95-01674
| INSP - Conference | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD95-01677
| INSP - Footings | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 - ftgs ok
|
MEC96-00823
| INSP - Conference | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 - CONF W/ DAVE L. RE VENTING OF W.H.& FURN KEEP C/N
|
BLD95-01591
| INSP - Set-back | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | | PASS |
|
|
/ / 340 - lc 10939 per gs...is sales office
|
BLD95-01770
| INSP - Framing/Rough-in | 3/20/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | A | PART |
|
|
03/20/96 340 - INSTALL OF HD'S, FIREBLOCKS AT DUCTS
|
BLD96-00243
| INSP - Framing/Rough-in | 3/20/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | A | FAIL |
|
|
03/20/96 340 - C/N...NEED MECH CORRECTIONS MADE OK TO INSUL
|
BLD96-00350
| INSP - Miscellaneous | 3/20/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | A | PASS |
|
|
03/20/96 340 - THERMAL BREAK FOR SLAB OK
|
BLD96-00610
| INSP - Framing/Rough-in | 3/20/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | A | PASS |
|
|
03/20/96 340 - ANYTIME AFTER 9:00 C/N OK
|
BLD96-00057
| INSP - Framing/Rough-in | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | PART |
|
|
03/21/96 340 - part, ok to insul
|
BLD96-00059
| INSP - Framing/Rough-in | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | PART |
|
|
03/21/96 340 - still need eng'g, ok to insul
|
BLD95-01677
| INSP - Foundation | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | FAIL |
|
|
03/21/96 340 - c/n, need 8'' wall at 2 story...ftg poured w/ 2 #4 bars o
|
BLD95-01604
| INSP - Final | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | PART |
|
|
03/21/96 340 - need horn wired to smoke dets...per townhouse ord. other items ok
|
MEC96-00224
| INSP - Final | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | NR |
|
|
03/21/96 340 - n/r need insul at plenums
|
MEC96-00224
| INSP - Final | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | NR |
|
|
03/21/96 340 - n/r need insul at plenums
|
MEC96-00843
| INSP - Rough-in & Gas Pressure | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | NR |
|
|
03/21/96 340 - 338 area
|
BLD95-01541
| INSP - Final | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | FAIL |
|
|
03/21/96 340 - FINAL c/n
|
BLD95-01588
| INSP - Final | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | FAIL |
|
|
03/21/96 340 - FINAL
|
BLD95-01591
| INSP - Final | 3/21/1996 | 3/21/1996 | 3/21/1996 12:00:00 AM | P | PASS |
|
|
03/21/96 340 - FINAL
|