PLM02-00426
| Plumbing Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PART |
|
|
###-#### HENRY ; I wrote correction on soap dispensors needing separate shutoffs. 3/21/2002 10:43:22 AM
|
PLM02-00653
| Plumbing Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | NR |
|
|
Scheduled by Inspector: 330 On 3/20/2002 2:33:34 PM
|
PLM02-00668
| Groundwork | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 14:36:16. Contact: ###-####.
|
PLM02-00597
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 17:12:57. Contact: ###-####.
|
PLM02-00597
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 17:12:57. Contact: ###-####.
|
PLM02-00701
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | NR |
|
|
###-####
|
PLM02-00703
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | NR |
|
|
|
PLM02-00704
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | NR |
|
|
|
PLM02-00698
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 09:32:17. Contact: ###-####.
|
PLM02-00699
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 09:33:15. Contact: ###-####.
|
PLM02-00705
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 09:34:08. Contact: ###-####.
|
PLM02-00706
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 09:34:55. Contact: ###-####.
|
PLM01-03890
| Final | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 09:58:15. Contact: ###-####.
|
PLM02-00575
| Plumbing Rough-in | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 10:05:38. Contact: ###-####.no approved plumbing plans or any indication of any routing to plumbing for plan approval?????call Bev or Louseie. Also need trap primers on floor drains. Notified Matt, plumber on job.
3/21/2002 12:29:27 PM
|
PLM02-00575
| Plumbing Rough-in | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 10:05:38. Contact: ###-####.no approved plumbing plans or any indication of any routing to plumbing for plan approval?????call Bev or Louseie. Also need trap primers on floor drains. Notified Matt, plumber on job.
3/21/2002 12:29:27 PM
|
PLM02-00533
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
###-#### ED
|
PLM02-00533
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
###-#### ED
|