PLM02-00370
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 12:00:36. Contact: ###-####.
|
PLM02-00210
| Plumbing Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 12:29:13. Contact: ###-####. new water line and over head water line test ok 3/21/2002 12:50:12 PM
|
PLM02-00558
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 12:35:09. Contact: ###-####. need approved size expansion tank for thermol expansion also before final need to see if structural will approve handicapped restroom oked temp 3/21/2002 2:47:55 PM
|
PLM02-00673
| Water and/or Sewer | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
###-#### SCOTT
|
PLM02-00378
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
fn insp- clayton -###-####
|
PLM02-00572
| Water and/or Sewer | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
###-#### PAULENE
|
PLM02-00360
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
###-#### KIRK
|
PLM01-04182
| Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 360 On 3/20/2002 1:02:47 PM
|
PLM02-00573
| Water Heater Final | 3/20/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 360 On 3/20/2002 1:04:34 PM after four p.m.
|
PLM01-03592
| Final | 3/18/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 03/18/2002 at 09:15:36. Contact: ###-####. 3/21/2002 3:59:28 PM tag and identify all back flow devices install protective cover,s under handicapp lav,s finish installation of equipment in basement 3/21/2002 6:01:01 PM
|
PLM02-00657
| Plumbing Rough-in | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 03/21/2002 at 07:44:10. Contact: ###-####.
|
PLM02-00700
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | CANC |
|
|
###-#### canc by inspector no water and sewer inspection 3/21/2002 4:55:10 PM
|
PLM02-00672
| Plumbing Rough-in | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | FAIL |
|
|
###-#### CRAIG air test on water failed 3/21/2002 2:04:31 PM
|
PLM02-00682
| Water and/or Sewer | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
###-#### EDDIE
|
PLM02-00644
| Sprinkler (Final) | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | FAIL |
|
|
###-#### RUSSELL need approved material,s for tie in on main water line 3/21/2002 5:09:43 PM
|
PLM02-00700
| Plumbing Rough-in | 3/21/2002 | 3/21/2002 | 3/21/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 360 On 3/21/2002 4:52:40 PM
|