BLD11-00051
| FIRE-Conference | 3/21/2011 | 3/21/2011 | 3/21/2011 3:28:39 PM | P | DONE |
|
|
Discussion with tenant on site regarding trade permit inspections, project approvals, fire life safety items, etc.
|
FIR11-00053
| INSP-Sprinkler Rough-in | 3/21/2011 | 3/21/2011 | 3/21/2011 3:25:10 PM | P | PART |
|
|
Verified insulation fill between joist spaces at the remodel area.
|
FIR11-00117
| INSP-Conference | 3/21/2011 | 3/21/2011 | 3/21/2011 3:22:30 PM | P | DONE |
|
|
Regarding spacing and coverage at cloud ceilings.
|
BLD10-02879
| FIRE-Final Inspection | 3/21/2011 | 3/21/2011 | 3/21/2011 3:20:49 PM | P | PASS |
|
|
Fire life safety inspection passed.
|
FIR10-00346
| FIR-Aging Inspection | 3/21/2011 | 3/21/2011 | 3/21/2011 12:08:27 PM | | NR |
|
|
No call for inspection
|
BLD11-00383
| FIRE-Final Inspection | 3/18/2011 | 3/21/2011 | 3/21/2011 12:06:54 PM | A | PASS |
|
|
Fire life safety passed with the exception of one surface bolt at the north exit door to be removed prior to occupancy as discussed.
|
FIR11-00116
| INSP-Final Inspection | 3/18/2011 | 3/21/2011 | 3/21/2011 12:02:32 PM | A | PASS |
|
|
Scope of work completed, fire alarm testing passed. Permit finaled.
|
BLD11-00043
| FIRE-Final Inspection | 3/18/2011 | 3/21/2011 | 3/21/2011 12:02:00 PM | P | PART |
|
|
Field verified insulation fill at the joist pockets above the south entry vestibule and exterior canopy areas.
|