BLD13-00181
| FIRE-Conference | 3/19/2014 | 3/19/2014 | | P | |
|
|
JC at phone #: ###-####
|
FIR14-00078
| INSP-Sprinkler Rough-in | 3/20/2014 | 3/21/2014 | 3/21/2014 5:01:43 PM | P | PART |
|
|
Overhead work at the grid ceilings approved for cover.
|
FIR13-00618
| INSP-Supply line flush | 3/20/2014 | 3/21/2014 | 3/21/2014 4:39:22 PM | P | PART |
|
|
UG fire supply line flush completed satisfactory.
|
BLD14-00534
| FIRE-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 4:24:33 PM | P | PASS |
|
|
Life safety passed. Screen walls to be verified at structural final.
|
BLD13-03578
| FIRE-Final Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 3:47:19 PM | P | PART |
|
|
Final pending door/hardware and project related FIR permit for access control relay. TCO okay per contractor agreement with S. Arellano.
|
FIR14-00150
| INSP-Final Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 3:41:06 PM | P | PASS |
|
|
Scope of work completed. Rough-in and final inspections passed. Fire sprinkler permit finaled.
|
FIR13-00620
| INSP-Final Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 3:39:32 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
BLD14-00220
| FIRE-Conference | 3/21/2014 | 3/21/2014 | 3/21/2014 2:45:25 PM | P | DONE |
|
|
On site discussion regarding fire life safety inspection items, project related FIR trade work, etc.
|
FIR13-00682
| INSP-Conference | 3/20/2014 | 3/21/2014 | 3/21/2014 2:21:18 PM | A | DEFR |
|
|
ray Phone #: ###-####
|
FIR14-00149
| INSP-Sprinkler Rough-in | 3/21/2014 | 3/21/2014 | 3/21/2014 2:20:28 PM | P | PART |
|
|
Overhead rough-in and demo work completed. Final pending ceiling and project finishes.
|
BLD14-00408
| FIRE-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 2:16:54 PM | A | PART |
|
|
|
BLD14-00408
| FIRE-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 2:15:34 PM | A | PART |
|
|
Project final pending completion of remodel work at the conference room and reception area. Remainder of office areas okayed. Exiting to be maintained as discussed.
|
BLD14-00633
| FIRE-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 2:11:33 PM | A | PASS |
|
|
Fire life safety finaled.
|
BLD14-00633
| FIRE-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 2:10:52 PM | A | PASS |
|
|
Fire life safety inspection passed.
|
BLD13-02720
| FIRE-Final Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 2:09:55 PM | P | PASS |
|
|
Fire life safety inspection completed. Need to post "door to remain..." signage at the main entry per review notes prior to structural final.
|
FIR13-00122
| INSP-Final Inspection | 3/19/2014 | 3/21/2014 | 3/21/2014 2:07:37 PM | A | NR |
|
|
|
FIR13-00620
| INSP-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 2:06:14 PM | A | PART |
|
|
Completed satisfactory air testing of the new dry system per NFPA 13 within allowable pressure loss at the guage.
|