ESC15-00033
| BMP Violation | 3/18/2016 | 3/21/2016 | 3/23/2016 10:43:49 AM | A | PART |
|
|
Check for sediment check dam bags closer to unfinished parking lot to prevent flow of turbid water down Auto Drive towards Cole.
DI on south side of Gratz has adequate sediment protection. DI on Auto Drive towards Cole has new gravel back check dam.
In process of preparing grading for paving the west parking lot. Some minor trackout. Will need street sweeping on Gratz this weekend.
Will check back next week for conditions and project completion.
|
ESC14-01040
| General Inspection | 3/21/2016 | 3/21/2016 | 3/22/2016 2:47:41 PM | | PEND |
|
|
Need to remove DI bag on Shelley
|
ESC16-00368
| Site Preparation | 3/21/2016 | 3/21/2016 | 3/21/2016 3:31:46 PM | P | PASS |
|
|
Kay-he has already dug Phone #: ###-####
Approved for construction to continue. BLD inspector will inspect ESC issues during footing inspection.
|
ESC16-00276
| Site Preparation | 3/21/2016 | 3/21/2016 | 3/21/2016 3:12:52 PM | P | PASS |
|
|
Jill Phone #: ###-####
Permit sign and SWPPP information posted. Work within irrigation canal ROW has already occurred in order to tile the ditch prior to construction.
Initial BMPs installed. Will check back on conditions early next week. Approved to start.
|
ESC15-00006
| DOC - Permit Finaled | 3/21/2016 | 3/21/2016 | 3/21/2016 2:47:06 PM | P | PASS |
|
|
|
ESC14-00588
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 2:16:37 PM | | PASS |
|
|
WIP. Site perimeter BMPs are installed. Stormwater pollution prevention team onsite at all times during construction. No significant trackout, construction entrance and rumble bars are currently in good condtion.
No corrections issued. Approved.
|
ESC13-00755
| Site Final | 3/21/2016 | 3/21/2016 | 3/21/2016 2:15:15 PM | P | PASS |
|
|
All temporary BMPs are now removed around the Terraces site as requested. All disturbed area stabilized.
Permit conditions satisfied. All ESC permits associated with the Terrances are now finaled out. Notified RP Preston.
|
ESC14-01059
| Aging Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 1:58:39 PM | | PART |
|
|
Request to clean up trackout in Boise Ave bike lane. RP stated he will have it swept up, but also stated he feels the trackout is from Dibble Excavation working on a BSU parcel.
Will check for cleanup later this week and follow with involved parties as necessary.
|
ESC15-00691
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 1:41:13 PM | | PASS |
|
|
WIP. Condos near completion. No trackout or discharges leaving site.
|
ESC15-00690
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 1:40:33 PM | | PASS |
|
|
WIP. Condos near completion. No trackout or discharges leaving site.
|
ESC15-00689
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 1:39:55 PM | | PASS |
|
|
WIP. Condos near completion. No trackout or discharges leaving site.
|
ESC15-00688
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 1:39:35 PM | | PASS |
|
|
WIP. Condos near completion. No trackout or discharges leaving site.
|
ESC15-00281
| DOC - Permit Finaled | 3/21/2016 | 3/21/2016 | 3/21/2016 12:13:48 PM | P | PASS |
|
|
Home complete, yard landscaped, all permits finaled. No temp BMP removal required/applicable. ESC permit condtions satisfied.
|
ESC15-00288
| Aging Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 12:13:21 PM | | PASS |
|
|
Home complete, yard landscaped, all permits finaled. No temp BMP removal required/applicable. ESC permit condtions satisfied.
|
ESC15-00288
| DOC - Permit Finaled | 3/21/2016 | 3/21/2016 | 3/21/2016 12:13:08 PM | P | PASS |
|
|
|
ESC15-00277
| Aging Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 12:12:53 PM | | PASS |
|
|
Home complete, yard landscaped, all permits finaled. No temp BMP removal required/applicable. ESC permit condtions satisfied.
|
ESC15-00277
| DOC - Permit Finaled | 3/21/2016 | 3/21/2016 | 3/21/2016 12:12:00 PM | P | PASS |
|
|
|
ESC16-00319
| Site Preparation | 3/18/2016 | 3/21/2016 | 3/21/2016 11:59:55 AM | A | PART |
|
|
Bill Phone #: ###-####
RP onsite to discuss project. Permit sign posted.
Excavation crew to re-install silt at runoff locations at the bottom of the site.
Silt fence not trenched in properly per specifications/construction detail.
RP stated excavation plan is leave vegetative buffer in tact around home excavation footprint.
Requested that perimeter BMP be re-installed properly. Some of silt fence installed up hill from construction is not necessary and may be remvoed. the two corners need work, I suggested installing wattles around the excavated disturbed area after initial hole is dug.
Inspection scheduled for 2 weeks to check BMPs
|
ESC15-00547
| Site Preparation | 3/21/2016 | 3/21/2016 | 3/21/2016 11:30:24 AM | P | PASS |
|
|
Jeremy Amar phone requested inpsection 3/18
Permit sign posted, SWPPP available onsite. Silt fence perimerter along Ustick installed. No work yet, construction entrance to be placed after initial grubbing and grading. Approved for construction of small 4 plex subdivision.
|
ESC15-00318
| Aging Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 11:16:45 AM | | PASS |
|
|
WIP on addtion. Near completion. No disturbed area at site, no loose sediment. ESC shall be finaled when BLD finaled. No corrections needed.
|
ESC16-00060
| Site Preparation | 3/18/2016 | 3/21/2016 | 3/21/2016 10:49:17 AM | A | PASS |
|
|
James Phone #: ###-####
Two projects at same facility including ADA upgrades and some pipe work on west side of building. Sheet flow drainage for work area is retained onsite. Onsite stormwater DIs have sediment protection. Additional wattles onsite for temporary perimeter stockpile control.
ESC permit signs posted at southwest corner of building. Approved for construction.
|
ESC16-00008
| Site Preparation | 3/18/2016 | 3/21/2016 | 3/21/2016 10:49:01 AM | A | PASS |
|
|
James Phone #: ###-####
Two projects at same facility including ADA upgrades and some pipe work on west side of building. Sheet flow drainage for work area is retained onsite. Onsite stormwater DIs have sediment protection. Additional wattles onsite for temporary perimeter stockpile control.
ESC permit signs posted at southwest corner of building. Approved for construction.
|
ESC13-00520
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 10:22:54 AM | | CANC |
|
|
|
ESC13-00707
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 10:22:45 AM | | CANC |
|
|
|
ESC16-00358
| Site Preparation | 3/21/2016 | 3/21/2016 | 3/21/2016 10:18:34 AM | P | PASS |
|
|
RP Pat ###-####
Permit sign to be posted on front of house. Low risk residential addition. Flat lot, low runoff potential. BMPs include housekeeping and concrete washout. RP familiar with permit conditions. Approved for construction.
|
ESC12-00206
| Aging Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 9:16:37 AM | | PASS |
|
|
WIP on SFHs by Habitat for Humanity on north end of culdesdac. Storm drains have sediment protection. Sites have good housekeeping. Approved.
|
ESC15-00701
| General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 8:37:23 AM | | PASS |
|
|
WIP on interior and finishing touches. Entrance off Orchard is now paved, no trackout or disharges. Permit sign posted in window. No corrections.
|